ODEION
J-01056 · Large works · 26 Oct 2026 → 18 Dec 2026

27 Stanley St - Mount Lawley - Matt & Mackenzie - Ens, Wall Removal & Floors

Contract (ex GST)
$164,591
$181,050 inc GST
Variations
$0
Budget (costings)
$131,302
80% of revenue
Committed (POs)
$1,048
1% of budget
Actual cost
$0
0% of budget
Claimed (received)
$10,698
7% · $153,893 raised, unpaid

Budget vs committed vs actual, by costing category

CategoryLinesBudgetCommitted (POs)ActualLeft in budgetUsed
L - 1 - Site Set-up / Pickups / Trade Assist / Supervision8$2,728$0$0$2,728
0%
L - 2 - Demolition & Earthworks5$7,513$0$0$7,513
0%
L - 3 - Footings, Concrete & Brickwork3$1,073$0$0$1,073
0%
L - 4 - Framing8$12,320$0$0$12,320
0%
L - 5 - Lock-up5$1,241$0$0$1,241
0%
L - 6 - Fixing6$4,771$0$0$4,771
0%
L - 7 - Completion3$931$0$0$931
0%
M - 10 - Flooring2$2,003$0$0$2,003
0%
M - 10 - Tiling3$4,005$0$0$4,005
0%
M - 11 - Cabinetry1$1,200$0$0$1,200
0%
M - 11 - Fixing Carpentry2$2,353$0$0$2,353
0%
M - 11 - Stone Tops1$1,936$0$0$1,936
0%
M - 13 - Bathroom Accessories2$1,630$0$0$1,630
0%
M - 13 - Electrical Selections2$1,550$0$0$1,550
0%
M - 13 - Fittings / Fixtures4$2,490$0$0$2,490
0%
M - 1 - Protection / Cleaning3$2,021$0$0$2,021
0%
M - 5 - Bricklaying1$250$0$0$250
0%
M - 5 - Structural Steels / Lintels3$4,668$0$0$4,668
0%
M - 6 - Framing / Eaves / Hardware4$3,369$0$0$3,369
0%
M - 8 - Tapware / Mixers2$1,550$0$0$1,550
0%
M - 9 - Insulation1$265$0$0$265
0%
M - 9 - Plastering2$382$0$0$382
0%
Post Stage – Handover / Maintenance / Warranty1$1,000$0$0$1,000
0%
Pre Stage - Construction Overheads9$20,277$0$0$20,277
0%
S - 10 - Flooring1$3,793$0$0$3,793
0%
S - 10 - Tiling11$6,438$0$0$6,438
0%
S - 12 - Painting6$12,586$0$0$12,586
0%
S - 13 - Shower Screens / Mirrors1$3,400$0$0$3,400
0%
S - 14 - Final Clean1$924$0$0$924
0%
S - 2 - Air Conditioning (HVAC)1$1,155$0$0$1,155
0%
S - 2 - Electrical11$4,119$0$0$4,119
0%
S - 2 - Plumbing2$7,950$0$0$7,950
0%
S - 3 - Hire - Excavator / Bobcat / Pump / Equipment2$1,345$0$0$1,345
0%
S - 7 - Roof Tiling1$1,200$0$0$1,200
0%
S - 7 - Windows1$750$0$0$750
0%
S - 9 - Plastering6$6,115$0$0$6,115
0%
POs not linked to a costing line–$0$1,048$0-$1,048
0%
Total$131,302$1,048$0$130,254

Wunderbuild vs Xero (supplier bills)

Xero is the ledger. Bills count here when a line is tracked to J-01056 or the bill is linked to one of this job's POs. Read only.

Actual cost, Wunderbuild (ex GST)
$0
Bills in Xero (ex GST)
$0
$0 inc GST · 0 bills
Difference (ex GST)
$0
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$0
0 bills with no PO link
DateSupplierBillStatusPOEx GSTInc GSTDue
Nothing mirrored yet.

Progress claims

ClaimDateStatusInc GSTOutstanding
PC-01264 Stage 1 - Deposit (6.5%) - on signing12 Oct 2026SENT$11,768$11,768
PC-01265 Stage 2 - Structural Works Complete, Part A (25%) - walls out, steel in and inspected3 Nov 2026DRAFT$45,263$45,263
PC-01266 Stage 3 - Framing & Rough-ins Complete (25%) - ensuite framed, window in, services roughed in11 Nov 2026DRAFT$45,263$45,263
PC-01267 Stage 4 - Tiling Complete (25%) - ensuite waterproofed and tiled, jarrah laid25 Nov 2026DRAFT$45,263$45,263
PC-01268 Stage 5 - Practical Completion (18.5%) - handover14 Dec 2026DRAFT$33,494$33,494

Variations

VariationStatusEx GST
Nothing mirrored yet.

Purchase orders (2)

POSupplierDateStatusEx GSTReceived
PO-03235 J-01056-LVLBig River Group Pty Ltd16 Oct 2026DRAFT · NONE$296$0
PO-03196 J-01056-STEELMetwest Steel13 Oct 2026SENT · NONE$752$0

Timesheets (0)

DateWhoHoursTask
Nothing mirrored yet.

Programme (37 items)

ItemStartEnd
PRE-START - engineering, steel order, long-lead orders (window, skylight, tiles) & permit follow-up12 Oct 202623 Oct 2026
DONE 14 Oct - Building permit issued - City of Vincent 6.2026.515.1 (hold point)14 Oct 202614 Oct 2026
MATERIAL DELIVERY - steel T-bar beam (Metwest PO-03196 / Q51151) delivered to site Fri 16 Oct (Jesse 15 Oct) + LVL beam (Big River, Duncan - date tbc, needed before steel install 5 Nov), posts & bearing pads16 Oct 202616 Oct 2026
Skip bin & temporary props hire (demo to steel install, props up until 12 Nov)20 Oct 20266 Nov 2026
L - 1 - Site set-up & protection: Ram Board, dust screens, furniture out; take in the Big River LVL, move the steel beam off the verge and inside (Jasper + Mike, Tue 20 Oct)20 Oct 202621 Oct 2026
Electrician - visit 1: disconnect, make safe & rough-in (ensuite, skylight, dining) (PowerFlex)22 Oct 202622 Oct 2026
Plumber - visit 1: disconnect & rough-in, sewer, waste & hot water run to the new ensuite (PS) (Warwick)22 Oct 202623 Oct 2026
L - 2 - Demolition: install propping, remove Wall 2 passage/dining and Wall 1 family/dining, fireplace & hearth, ensuite strip-out23 Oct 202629 Oct 2026
L - 4 - Structural steel: lift, fix & pack T-bar beam + LVL beam and posts, strike props30 Oct 20262 Nov 2026
Structural engineer site inspection before cover-up (hold point)3 Nov 20263 Nov 2026
Bricklayer - brick up existing door & fireplace, form ensuite window reveals & sill (BNA)3 Nov 20263 Nov 2026
MATERIAL DELIVERY - framing timber, subfloor joists & sheeting, jarrah boards, skylight shaft framing3 Nov 20263 Nov 2026
L - 4 - Ensuite stud walls, nib & niche; subfloor set-down; jarrah floor extension & repairs; skylight shaft4 Nov 202610 Nov 2026
MATERIAL DELIVERY - ensuite window & VELUX skylight 1140x700 (Duncan)10 Nov 202610 Nov 2026
L - 5 - Install ensuite window, flashings, reveals & sill; fit VELUX skylight11 Nov 202611 Nov 2026
AC - rough-in11 Nov 202611 Nov 2026
MATERIAL DELIVERY - insulation & Villaboard11 Nov 202611 Nov 2026
Roof tiler - skylight tile-roof flashing & tie-in (Mitre Roofing)12 Nov 202612 Nov 2026
L - 5 - Insulation & wet-area blocking12 Nov 202612 Nov 2026
Plasterer - Villaboard, plasterboard, bulkheads, decorative cornice, skylight square-set & crack repairs (PS) (Emberforge)13 Nov 202618 Nov 2026
MATERIAL DELIVERY - tiles, adhesive & grout, feature tile (Duncan)18 Nov 202618 Nov 2026
Tiler - waterproofing & tiling: ensuite floor, walls & vanity feature wall19 Nov 202625 Nov 2026
L - 6 - Cabinetry measure: floating vanity 1730 (Brad)19 Nov 202619 Nov 2026
MATERIAL DELIVERY - fixout: 140 mm splayed skirting, architraves, ensuite door & hardware25 Nov 202625 Nov 2026
MATERIAL DELIVERY - cabinetry materials (Brad)25 Nov 202625 Nov 2026
L - 6 - Fixout: 140 mm skirtings & make-good trims, hang ensuite door, ease & adjust doors26 Nov 202630 Nov 2026
L - 6 - Cabinetry install: floating vanity (Brad)26 Nov 202626 Nov 2026
Painter - ensuite, dining, passage, bedrooms 1-3, family & laundry passage walls, ceilings & trims1 Dec 20264 Dec 2026
Stone vanity top supply & install (lead squeezed to 1 week for the Christmas finish)3 Dec 20263 Dec 2026
MATERIAL DELIVERY - tapware, toilet suite, basin, shower tray, niche, accessories, LED mirror, towel rails, light fittings (Duncan)3 Dec 20263 Dec 2026