J-01055 · Small works · 19 Oct 2026 → 12 Nov 2026

Jane Johnson - 8 MacMillan Rise, Duncraig - Wall Removal & New Walls

Contract (ex GST)
$40,759
$44,835 inc GST
Variations
$0
Budget (costings)
$40,759
100% of revenue
Committed (POs)
$750
2% of budget
Actual cost
$0
0% of budget
Claimed (received)
$14,724
36% · $26,035 raised, unpaid

Budget vs committed vs actual, by costing category

CategoryLinesBudgetCommitted (POs)ActualLeft in budgetUsed
A. Structural wall removal, two openings and the low wall planter7$33,350$0$0$33,350
0%
B. New walls and doorway, 11.0 lineal metres4$7,409$0$0$7,409
0%
POs not linked to a costing line–$0$750$0-$750
0%
Total$40,759$750$0$40,009

Wunderbuild vs Xero (supplier bills)

Xero is the ledger. Bills count here when a line is tracked to J-01055 or the bill is linked to one of this job's POs. Read only.

Actual cost, Wunderbuild (ex GST)
$0
Bills in Xero (ex GST)
$0
$0 inc GST · 0 bills
Difference (ex GST)
$0
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$0
0 bills with no PO link
DateSupplierBillStatusPOEx GSTInc GSTDue
Nothing mirrored yet.

Progress claims

ClaimDateStatusInc GSTOutstanding
PC-01257 Deposit on acceptance - invoiced as INV-0625, paid1 Oct 2026RECEIVED$4,988$0
PC-01258 Claim 1 - Council submission lodged and materials ordered (25%)9 Oct 2026SENT$11,209$11,209
PC-01259 Claim 2 - Mobilised on site, protection complete (25%)2 Nov 2026DRAFT$11,209$11,209
PC-01260 Claim 3 - Beams installed, propping removed, new walls framed (25%)12 Nov 2026DRAFT$11,209$11,209
PC-01261 Claim 4 - Practical completion (balance of contract)26 Nov 2026DRAFT$6,121$6,121

Variations

VariationStatusEx GST
Nothing mirrored yet.

Purchase orders (1)

POSupplierDateStatusEx GSTReceived
PO-03236 J-01055-LVLBig River Group Pty Ltd16 Oct 2026DRAFT · NONE$750$0

Timesheets (0)

DateWhoHoursTask
Nothing mirrored yet.

Programme (16 items)

ItemStartEnd
Pre-start - council lodgement (structural, City of Joondalup - lodged 5 Oct, fee paid 6 Oct), engineer's cert, LVL & timber orders5 Oct 20269 Oct 2026
GOAL - Building approval issued + steels (LVL beams) on site - Tuan (hold point)16 Oct 202616 Oct 2026
MATERIAL DELIVERY - two 300x63 LVL13 beams 6.0m (Big River PO J-01055-LVL, delivery Tue 20 Oct), brackets & framing timber20 Oct 202620 Oct 2026
Site set-up & house protection - dust walls, floor protection over slate2 Nov 20262 Nov 2026
Electrician - visit 1: disconnect & make safe in walls coming out, oven out3 Nov 20263 Nov 2026
Propping & demolition - ceiling strips, prop both sides, two walls & low planter out, disposal4 Nov 20266 Nov 2026
Install two 600x63 LVL beams flush, bolt to existing, reframe ceiling both sides, props out9 Nov 202610 Nov 2026
New wall frames 11 lm & door opening11 Nov 202612 Nov 2026
Electrician - visit 2: rough-in & relocate services13 Nov 202613 Nov 2026
Insulation to new walls16 Nov 202616 Nov 2026
Plasterer - board new walls, patch ceiling strips, cornice, flush & set17 Nov 202619 Nov 2026
MATERIAL DELIVERY - fixing materials (jamb & architraves)19 Nov 202619 Nov 2026
Fixing carpentry - opening trims & architraves (no door or hardware - JC)20 Nov 202620 Nov 2026
Painter - seal & two coats, new walls & patched areas23 Nov 202624 Nov 2026
Electrician - visit 3: fit-off & compliance certificate25 Nov 202625 Nov 2026
Final clean & practical completion (hold point)26 Nov 202626 Nov 2026