J-01053 · Large works · 27 Sept 2026 → 22 Dec 2026

1 Glanville street - Mosman Park - James & Hannah - Ext & Ren

Contract (ex GST)
$320,332
$352,365 inc GST
Variations
$0
Budget (costings)
$268,364
84% of revenue
Committed (POs)
$41,850
16% of budget
Actual cost
$17,496
7% of budget
Claimed (received)
$0
0% · $320,332 raised, unpaid

Budget vs committed vs actual, by costing category

CategoryLinesBudgetCommitted (POs)ActualLeft in budgetUsed
BuiltEco - Head Contractor Fee (5%) & HII10$20,798$0$5,823$14,976
28%
L - 1 - Site Set-up / Pickups / Trade Assist / Supervision11$24,747$0$644$24,102
3%
L - 2 - Demolition & Earthworks18$7,240$0$357$6,883
5%
L - 3 - Footings, Concrete & Brickwork18$3,486$0$0$3,486
0%
L - 4 - Framing18$17,129$0$0$17,129
0%
L - 5 - Lock-up7$3,476$0$0$3,476
0%
L - 6 - Fixing19$8,073$0$0$8,073
0%
L - 7 - Completion5$8,886$0$0$8,886
0%
M - 10 - Tiling4$3,595$0$1,660$1,935
46%
M - 11 - Cabinetry18$21,000$0$0$21,000
0%
M - 11 - Fixing Carpentry16$17,912$0$0$17,912
0%
M - 11 - Stone Tops1$909$0$0$909
0%
M - 13 - Electrical Selections1$2,000$0$0$2,000
0%
M - 13 - Fittings / Fixtures3$2,982$0$261$2,721
9%
M - 1 - Site Prelims10$5,400$0$171$5,229
3%
M - 4 - Concrete23$2,198$0$0$2,198
0%
M - 5 - Bricklaying10$1,179$0$0$1,179
0%
M - 5 - Structural Steels / Lintels1$98$0$0$98
0%
M - 6 - Framing / Eaves / Hardware21$6,504$0$0$6,504
0%
M - 9 - Insulation1$630$0$0$630
0%
M - 9 - Plastering1$273$0$0$273
0%
Post Stage – Handover / Maintenance / Warranty1$2,180$0$0$2,180
0%
Pre Stage - Construction Overheads10$11,592$0$1,105$10,488
10%
S - 10 - Flooring2$12,291$0$0$12,291
0%
S - 10 - Tiling17$8,658$0$0$8,658
0%
S - 11 - Stone Mason1$2,727$0$0$2,727
0%
S - 12 - Painting2$11,323$0$0$11,323
0%
S - 13 - Shower Screens / Mirrors2$1,841$0$0$1,841
0%
S - 2 - Air Conditioning (HVAC)2$1,550$0$0$1,550
0%
S - 2 - Electrical14$8,754$0$0$8,754
0%
S - 2 - Plumbing4$5,182$0$0$5,182
0%
S - 3 - Hire - Excavator / Bobcat / Pump / Equipment12$5,467$0$0$5,467
0%
S - 4 - Termite Treatments3$792$0$0$792
0%
S - 7 - Roof Plumbing8$5,545$0$0$5,545
0%
S - 7 - Roof Tiling1$3,888$0$0$3,888
0%
S - 7 - Windows4$19,042$0$7,475$11,567
39%
S - 9 - Plastering12$6,782$0$0$6,782
0%
S - 9 - Rendering2$1,738$0$0$1,738
0%
Uncategorised1$496$0$0$496
0%
POs not linked to a costing line–$0$41,850$0-$41,850
0%
Total$268,364$41,850$17,496$226,514

Wunderbuild vs Xero (supplier bills)

Xero is the ledger. Bills count here when a line is tracked to J-01053 or the bill is linked to one of this job's POs. Read only.

Actual cost, Wunderbuild (ex GST)
$17,496
Bills in Xero (ex GST)
$18,280
$20,037 inc GST · 11 bills
Difference (ex GST)
$784
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$9,284
11 bills with no PO link
DateSupplierBillStatusPOEx GSTInc GSTDue
15 Oct 2026Versatile Building Products10108798AUTHORISEDnone$4,136$4,550$4,550
14 Oct 2026Tile Empire726970AUTHORISEDnone$1,778$1,955$1,955
14 Oct 2026PowerFlex Electrical Pty Ltd11335DRAFTnone$1,356$1,492$1,492
14 Oct 2026Kantili66244PAIDnone$1,660$1,826$0
12 Oct 2026CUSTOM SCREENSINV-00146724PAIDnone$7,475$8,223$0
7 Oct 2026Harvey Norman Commercial7019327AUTHORISEDnone$261$287$287
6 Oct 2026Bunnings Group Limited2433/00869039AUTHORISEDnone$7$8$8
6 Oct 2026Bunnings Group Limited2010/01208957AUTHORISEDnone$164$181$181
25 Sept 2026Construction Training FundINV-392479-G1X2J2PAIDnone$705$705$0
15 Sept 2026West Reo Supply2627-OD01AUTHORISEDnone$338$372$372
15 Sept 2026Termico Certifications59206AUTHORISEDnone$400$440$440

Progress claims

ClaimDateStatusInc GSTOutstanding
PC-01247 Claim 1 of 9 - Deposit (6.5% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoiced BuiltEco INV-0617 at this stage less 5% and less the HII credit.20 Sept 2026DRAFT$22,904$22,904
PC-01248 Claim 2 of 9 - Site Establishment (20% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.13 Oct 2026DRAFT$70,473$70,473
PC-01249 Claim 3 of 9 - Slab / Subfloor (15% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.23 Oct 2026DRAFT$52,855$52,855
PC-01250 Claim 4 of 9 - Structural Walls (10% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.13 Nov 2026DRAFT$35,237$35,237
PC-01251 Claim 5 of 9 - Roof Cover (10% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.2 Dec 2026DRAFT$35,237$35,237
PC-01252 Claim 6 of 9 - Wet Area Tiling (10% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.11 Dec 2026DRAFT$35,237$35,237
PC-01253 Claim 7 of 9 - Cabinetry & Stone (10% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.22 Dec 2026DRAFT$35,237$35,237
PC-01254 Claim 8 of 9 - Painting & Finishes (10% of contract) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.15 Jan 2027DRAFT$35,237$35,237
PC-01255 Claim 9 of 9 - Practical Completion (8.5% of contract, balance) - BuiltEco head contract stage. Internal record: BuiltEco invoices the client; ODEION invoices BuiltEco at this stage less 5%.29 Jan 2027DRAFT$29,951$29,951

Variations

VariationStatusEx GST
VO-1132 Bedroom 1 & 2 robe changesDRAFT$4,020
VO-1134 Bathroom slab replacementDRAFT$2,664

Purchase orders (14)

POSupplierDateStatusEx GSTReceived
PO-03234 J-01053-REOWest Reo Supply16 Oct 2026DRAFT · NONE$0$0
PO-03193 J-01053-WINDOWSCustom Windows12 Oct 2026PARTIALLY_RECEIVED · APPROVED$14,950$7,475
PO-03083 J-01053-PLUMBINGWP Services W.A12 Oct 2026SENT · NONE$4,091$0
PO-03182 Big River Group Pty Ltd9 Oct 2026SENT · NONE$3,086$0
PO-03150 7019327Harvey Norman Commercial7 Oct 2026RECEIVED · APPROVED$261$261
PO-03197 2010/01208957Bunnings Group Limited6 Oct 2026RECEIVED · APPROVED$164$164
PO-03198 2433/00869039Bunnings Group Limited6 Oct 2026RECEIVED · APPROVED$7$7
PO-03105 J-01053-TILES-KANTILIKantili2 Oct 2026RECEIVED · APPROVED$1,660$1,660
PO-03106 J-01053-TILES-TILEEMPIRETile Empire2 Oct 2026SENT · NONE$1,778$0
PO-03104 J-01053-STEELMetwest Steel2 Oct 2026SENT · NONE$2,975$0
PO-03085 J-01053-PLASTERINGEmberforge Pty Ltd1 Oct 2026DRAFT · NONE$6,350$0
PO-03084 J-01053-ELECTRICALPowerFlex Electrical Pty Ltd1 Oct 2026SENT · NONE$5,424$0
PO-03170 INV-392479-G1X2J2Construction Training Fund25 Sept 2026RECEIVED · APPROVED$705$705
PO-03158 59206Termico Certifications15 Sept 2026RECEIVED · APPROVED$400$400

Timesheets (8)

DateWhoHoursTask
7 Oct 2026Jasper Osabofu0.75Pickup - extra rug and driveway protection timber from Turriff (Floreat) for Glanville
7 Oct 2026Jasper Osabofu3.25Demolition - bathroom floor tiles & screed up, pack-up. Finished task.
6 Oct 2026Jasper Osabofu3.50Site set-up & protection - tools from Carbridge, ram board/tape from Bunnings, rugs, ram board, zip doors
6 Oct 2026Jasper Osabofu5.25Demolition - bathroom strip-out, bath out, bricks out of shower/bath; floor tiles and screed left for tomorrow
24 Sept 2026Telaufue Pou1.251 Glanville, Mosman Park. Dropped off carpet that I wasnt able to yesterday.
23 Sept 2026Telaufue Pou2.001 Glanville St, Mossman Park. Drop off temp fence material. Had break near Jesses house. Picked up carpet for site from Jesses house.
1 Sept 2026Brad Johns1.00Brad Johns - Mosman Park prelims
24 July 2026Brad Johns2.00Brad Johns - Mosman Park meeting

Programme (60 items)

ItemStartEnd
Pre-start - material planning & long-lead orders (windows, roof tiles via Mitre, frames)28 Sept 20262 Oct 2026
MATERIAL DELIVERY - site prelims (fence panels, signage, profiles, floor protection; toilet ordered)8 Oct 20268 Oct 2026
L - 1 - Site set-up & protection8 Oct 20269 Oct 2026
MATERIAL DELIVERY - skip bins (laneway, verge permit) & demo hire (jackhammer, props)9 Oct 20269 Oct 2026
Electrician - visit 1: disconnect, make safe & rough-in (inside)12 Oct 202612 Oct 2026
Air conditioning - rough-in (split system)13 Oct 202613 Oct 2026
L - 2 - Demolition & strip-out (bathroom, ceilings, brickwork openings) - power points & lights left in place19 Oct 202623 Oct 2026
MATERIAL DELIVERY - Maxi bricks (Tuan), sand, Brickies Light & brick accessories (Mitre 10 - Dan, ordered 16 Oct); lintels on Metwest PO19 Oct 202619 Oct 2026
MATERIAL DELIVERY - framing timber, roof framing, LVLs & fixings (Big River - Tuan ordering)20 Oct 202620 Oct 2026
L - 4 - Internal wall framing, blocking & wet-area set-out (inside stream)21 Oct 202623 Oct 2026
MATERIAL DELIVERY - Harvey Norman Commercial order 1: mixer bodies & bathroom rough-in items (Duncan - needed before inside rough-in)23 Oct 202623 Oct 2026
MATERIAL DELIVERY - insulation batts23 Oct 202623 Oct 2026
Plumber - visit 1: inside rough-in (bathroom, laundry, kitchen) + external drainage & trenching - one visit26 Oct 202626 Oct 2026
Plasterer - insulation install (batts supplied by Odeion) & wet-area blocking check (inside)26 Oct 202626 Oct 2026
L - 2 - Earthworks, footing & pier trenches by hand (outside stream)26 Oct 202627 Oct 2026
MATERIAL DELIVERY - reo, formwork & concrete (footings & piers)26 Oct 202626 Oct 2026
Plasterer - visit 1: inside (bathroom Villaboard, internal board & cornice)27 Oct 202629 Oct 2026
L - 3 - Footings & piers pour (patio extension, no slab) + any internal infill27 Oct 202628 Oct 2026
Footings cure hold29 Oct 202630 Oct 2026
Brad - cabinetry measure (robes & studies, inside)30 Oct 202630 Oct 2026
MATERIAL DELIVERY - tiles (Kantili / Tile Empire, Duncan)30 Oct 202630 Oct 2026
MATERIAL DELIVERY - structural steel & lintels (Metwest, HDG - Duncan)30 Oct 202630 Oct 2026
Tiler - waterproof & tile bathroom (one trip)2 Nov 20266 Nov 2026
L - 3 - Brickwork - extension walls, sills, lintels & join to existing2 Nov 20264 Nov 2026
L - 4 - Wall frames, wrap & join to existing (outside stream)5 Nov 20269 Nov 2026
MATERIAL DELIVERY - cabinetry (vanity, robes, studies - Brad)9 Nov 20269 Nov 2026
Brad - cabinetry install (vanity, robes & studies) - straight after tiling10 Nov 202611 Nov 2026
Scaffold / aluminium towers hire - decide Fri 2 Oct (roof frame to roof tiler)10 Nov 202624 Nov 2026
L - 4 - Roof frame, tie into existing roof & fascia (patio extension)10 Nov 202616 Nov 2026
MATERIAL DELIVERY - VELUX skylights & drypan flashings (Tuan - ordered)11 Nov 202611 Nov 2026