ODEION
J-01050 · Small works · 7 Sept 2026 → 19 Oct 2026

Rachel Chew - 152 Mars Street, Carlisle - Bathroom & WC Renovation

Contract (ex GST)
$23,600
$25,960 inc GST
Variations
$27,261
Budget (costings)
$48,448
95% of revenue
Committed (POs)
$32,839
68% of budget
Actual cost
$17,154
35% of budget
Claimed (received)
$40,595
80% · $10,266 raised, unpaid

Budget vs committed vs actual, by costing category

CategoryLinesBudgetCommitted (POs)ActualLeft in budgetUsed
A. Builder's works - fixed price8$9,808$0$2,621$7,187
27%
B. Provisional sums - client selections6$9,435$0$7,934$1,501
84%
C. Slab demolition and re-pour - variation19$12,541$0$456$12,084
4%
D. Bricklaying - omitted at quote1$0$0$134-$134
0%
Variation 011169$5,262$0$6,009-$747
114%
Variation 011276$6,785$0$0$6,785
0%
Variation 011282$2,800$0$0$2,800
0%
Variation 011314$1,818$0$0$1,818
0%
POs not linked to a costing line–$0$32,839$0-$32,839
0%
Total$48,448$32,839$17,154$15,609

Wunderbuild vs Xero (supplier bills)

Xero is the ledger. Bills count here when a line is tracked to J-01050 or the bill is linked to one of this job's POs. Read only.

Actual cost, Wunderbuild (ex GST)
$17,154
Bills in Xero (ex GST)
$20,422
$22,464 inc GST · 11 bills
Difference (ex GST)
$3,268
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$16,538
11 bills with no PO link
DateSupplierBillStatusPOEx GSTInc GSTDue
14 Oct 2026CERAMIC TILE SUPPLIES121731AUTHORISEDnone$1,325$1,457$1,457
14 Oct 2026Tradelink20379794AUTHORISEDnone$4,684$5,153$5,153
12 Oct 2026Holcim Australia9410599340AUTHORISEDnone$820$901$901
10 Oct 2026Bunnings Group Limited2404/00298528AUTHORISEDnone$150$165$165
5 Oct 2026Elexa Plumbing and Gas5879DRAFTnone$6,407$7,048$7,048
30 Sept 2026Instant Products Hire238781AUTHORISEDnone$151$166$166
30 Sept 2026Instant Waste Management5231986AUTHORISEDnone$696$766$766
29 Sept 2026PowerFlex Electrical Pty Ltd11327PAIDnone$453$499$0
25 Sept 2026Elexa Plumbing and Gas5822PAIDnone$3,000$3,300$0
25 Sept 2026Elexa Plumbing and Gas5822APAIDnone$1,934$2,128$0
18 Sept 2026Bunnings Group Limited2010/01286905AUTHORISEDnone$802$882$882

Progress claims

ClaimDateStatusInc GSTOutstanding
PC-01201 Claim 1 - Site setup complete (25%)22 Sept 2026RECEIVED$6,490$0
PC-01202 Claim 2 - Demolition complete (25%)22 Sept 2026RECEIVED$6,490$0
PC-01200 Deposit on acceptance and signing of contract (6.5%)22 Sept 2026RECEIVED$1,687$0
PC-01256 Additional Concrete & Selection Variations1 Oct 2026RECEIVED$15,205$0
PC-01262 Additional Drainage Variation9 Oct 2026RECEIVED$9,703$0
PC-01263 Bathroom Plumbing Allowance Variation (at cost, no margin)12 Oct 2026RECEIVED$3,080$0
PC-01269 Kitchen Doorway Lintel Variation14 Oct 2026SENT$2,000$2,000
PC-01203 Claim 3 - Tiling complete (25%)28 Oct 2026DRAFT$6,490$6,490
PC-01204 Claim 4 - Practical completion and handover (18.5%)27 Nov 2026DRAFT$4,803$4,803

Variations

VariationStatusEx GST
VO-1116 Window alteration/install, additional electrical, tiling and selection adjustmentsAPPROVED_BY_BUILDER$6,213
VO-1118 Bathroom and external slab demolition and re-pourAPPROVED_BY_BUILDER$7,610
VO-1127 Additional drainage - replace root-damaged external drainsAPPROVED_BY_BUILDER$8,821
VO-1128 Bathroom plumbing allowance adjustment - toilet, vanity, bath and shower (at cost)APPROVED_BY_BUILDER$2,800
VO-1131 Kitchen doorway - remove door frame and install new lintel beamAPPROVED_BY_BUILDER$1,818

Purchase orders (13)

POSupplierDateStatusEx GSTReceived
PO-03237 J-01050-TILING-BAbots Tiling19 Oct 2026SENT · NONE$9,500$0
PO-03232 121731CERAMIC TILE SUPPLIES14 Oct 2026RECEIVED · APPROVED$1,325$1,325
PO-03231 20379794Tradelink14 Oct 2026RECEIVED · APPROVED$4,684$4,684
PO-03220 J-01050-WINDOWSWest Coast Window Installations13 Oct 2026SENT · NONE$1,964$0
PO-03218 2404/00298528Bunnings Group Limited10 Oct 2026RECEIVED · APPROVED$150$150
PO-03149 5231986Instant Waste Management30 Sept 2026RECEIVED · APPROVED$696$696
PO-03116 238781Instant Products Hire30 Sept 2026RECEIVED · APPROVED$151$151
PO-03036 5822AElexa Plumbing and Gas25 Sept 2026RECEIVED · APPROVED$1,934$1,934
PO-02863 J-01050-PAINTINGCoastal Colours Painting22 Sept 2026SENT · NONE$364$0
PO-02858 J-01050-PLUMBINGElexa Plumbing and Gas22 Sept 2026RECEIVED · APPROVED$6,000$6,000
PO-02855 J-01050-ELECTRICALPowerFlex Electrical Pty Ltd22 Sept 2026PARTIALLY_RECEIVED · APPROVED$906$453
PO-02860 J-01050-TILINGPeter Randall Tiling Services22 Sept 2026CANCELLED · NONE$4,690$0
PO-02996 J-01050-BRICKWORKBNA Bricklaying22 Sept 2026SENT · NONE$475$0

Timesheets (7)

DateWhoHoursTask
16 Oct 2026Jasper Osabofu2.00Mars St - bathroom ceiling up with Mike
16 Oct 2026Jasper Osabofu3.00Mars St - Bunnings materials, bricklaying nib & window with Mike
12 Oct 2026Telaufue Pou6.33Mars St - tools pickup, prep, barrow concrete pour & clean-up
12 Oct 2026Jasper Osabofu5.00Mars St - slab pour prep, plastic, mesh & pour
24 Sept 2026Jasper Osabofu8.25Demolition, strip-out and disposal
18 Sept 2026Jasper Osabofu9.00Demolition, strip-out and disposal
17 Sept 2026Jasper Osabofu8.50Demolition, strip-out and disposal

Programme (31 items)

ItemStartEnd
Brad measure up - vanity, window reveal cabinet and mirror cabinet7 Sept 20267 Sept 2026
Showroom selections with Duncan8 Sept 20269 Sept 2026
Plumber - site scope & drain camera assessment (done)8 Sept 20268 Sept 2026
Final contract price, contract and home indemnity insurance10 Sept 202610 Sept 2026
Order tiles, fixtures, tapware and joinery10 Sept 202611 Sept 2026
Client away - no client decisions this week14 Sept 202618 Sept 2026
Site protection, access and skip bin22 Sept 202622 Sept 2026
Demolition and strip out - bathroom, WC and existing ceiling23 Sept 202624 Sept 2026
Electrician - visit 1: disconnect, make safe & rough-in (done)29 Sept 202629 Sept 2026
MATERIAL DELIVERY - tiles (Duncan) - booked with CTS, into garage2 Oct 20262 Oct 2026
Plumber - visit 1: drainage & rough-in5 Oct 20266 Oct 2026
MATERIAL DELIVERY - concrete 1.2 m3 25MPa, early pour12 Oct 202612 Oct 2026
Slab re-pour - bathroom & external (variation V-01118)12 Oct 202612 Oct 2026
Slab cure (hold) - tiler walls first, floor screed late in his visit13 Oct 202619 Oct 2026
Odeion (Mike) - nib wall & brick up around window (done, per Jesse 19 Oct)16 Oct 202616 Oct 2026
Odeion (Mike) - hang ceiling, pre-tiling bits (done, per Jesse 19 Oct)19 Oct 202619 Oct 2026
Tiler - screed, waterproofing & tiling, bathroom & WC (one trip) (Martin, Abots Tiling) - asked to start Wed 21 or late Tue 20 (mixer move by Alex), awaiting reply20 Oct 202628 Oct 2026
Window site measure - 11:30am (booked)21 Oct 202621 Oct 2026
Odeion (Tirrus) - kitchen doorway: remove door frame & install lintel beam (variation V-01131)23 Oct 202623 Oct 2026
MATERIAL DELIVERY - vanity, window reveal cabinet & mirror cabinet (Brad)28 Oct 202628 Oct 2026
Cabinetry install - vanity, window reveal cabinet & mirror cabinet (Brad)29 Oct 202629 Oct 2026
Plasterer (Kwan, Emberforge) - flush ceiling sheets, cornice, patch & make good29 Oct 202629 Oct 2026
Painter - ceiling & cornice, one visit30 Oct 202630 Oct 2026
MATERIAL DELIVERY - Beacon Lighting order (paid) - site receiver TBC12 Nov 202612 Nov 2026
Stone benchtop - vanity top supply & install (Brad organises)13 Nov 202613 Nov 2026
MATERIAL DELIVERY - fixtures, tapware & accessories (Duncan)13 Nov 202613 Nov 2026
Plumber - visit 2: fit-off & compliance16 Nov 202616 Nov 2026
Electrician - visit 2: fit-off & compliance certificate16 Nov 202616 Nov 2026
Shower screen - measure after tiling, supply & install (4 wk lead)26 Nov 202626 Nov 2026
Final clean, certificates & practical completion (hold point)27 Nov 202627 Nov 2026