ODEION
J-01048 · Large works · 4 Oct 2026 → 9 Mar 2027

7 Hawdon Mews - George & Clare Eskander - Hillarys - Ren

Contract (ex GST)
$467,656
$514,421 inc GST
Variations
$0
Budget (costings)
$360,929
77% of revenue
Committed (POs)
$400
0% of budget
Actual cost
$815
0% of budget
Claimed (received)
$0
0% · $467,656 raised, unpaid

Budget vs committed vs actual, by costing category

CategoryLinesBudgetCommitted (POs)ActualLeft in budgetUsed
L - Provisional Sums & Allowances (no timesheets)7$12,727$0$0$12,727
0%
L - Site Labour (all Odeion crew hours)8$59,489$0$415$59,074
1%
M - 10 - Flooring1$7,215$0$0$7,215
0%
M - 10 - Tiling1$91$0$0$91
0%
M - 11 - Cabinetry - Materials1$33,273$0$0$33,273
0%
M - 11 - Fixing Carpentry2$6,520$0$0$6,520
0%
M - 13 - Appliances6$5,589$0$0$5,589
0%
M - 13 - Bathroom Accessories3$289$0$0$289
0%
M - 13 - Electrical Selections2$2,091$0$0$2,091
0%
M - 13 - Fittings / Fixtures3$1,954$0$0$1,954
0%
M - 1 - Site Prelims3$4,851$0$0$4,851
0%
M - 3 - Retaining1$30,074$0$0$30,074
0%
M - 4 - Bricklaying1$1,111$0$0$1,111
0%
M - 4 - Concrete1$5,529$0$0$5,529
0%
M - 4 - Structural Steels / Lintels2$3,455$0$0$3,455
0%
M - 6 - Framing / Eaves / Hardware1$2,265$0$0$2,265
0%
M - 7 - Roof Cover1$2,795$0$0$2,795
0%
M - 7 - Roof Plumbing1$3,574$0$0$3,574
0%
M - 8 - Tapware / Mixers3$1,474$0$0$1,474
0%
M - 9 - Insulation1$311$0$0$311
0%
*** Phase 1 - Materials1$2,247$0$0$2,247
0%
*** Phase 2 - Materials1$2,247$0$0$2,247
0%
Post Stage – Handover / Maintenance / Warranty1$3,149$0$0$3,149
0%
Pre Stage - Construction Overheads13$22,701$0$400$22,301
2%
S - 10 - Flooring3$3,998$0$0$3,998
0%
S - 11 - Cabinetry - Stone1$19,123$0$0$19,123
0%
S - 12 - Painting1$14,099$0$0$14,099
0%
S - 13 - Screening & Fencing1$1,033$0$0$1,033
0%
S - 14 - Final clean1$1,791$0$0$1,791
0%
S - 2 - Air Conditioning (HVAC)2$20,727$0$0$20,727
0%
S - 2 - Electrical3$5,955$0$0$5,955
0%
S - 2 - Plumbing2$7,165$0$0$7,165
0%
S - 3 - Hire - Excavator / Bobcat / Pump / Equipment1$573$0$0$573
0%
S - 4 - Termite Treatments1$372$0$0$372
0%
S - 7 - Roof Plumbing1$2,108$0$0$2,108
0%
S - 7 - Windows4$51,331$0$0$51,331
0%
S - 9 - Plastering1$4,578$0$0$4,578
0%
S - 9 - Rendering1$13,055$0$0$13,055
0%
POs not linked to a costing line–$0$400$0-$400
0%
Total$360,929$400$815$360,114

Wunderbuild vs Xero (supplier bills)

Xero is the ledger. Bills count here when a line is tracked to J-01048 or the bill is linked to one of this job's POs. Read only.

Actual cost, Wunderbuild (ex GST)
$815
Bills in Xero (ex GST)
$400
$440 inc GST · 1 bills
Difference (ex GST)
-$415
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$440
1 bills with no PO link
DateSupplierBillStatusPOEx GSTInc GSTDue
1 Sept 2026Termico Certifications59204AUTHORISEDnone$400$440$440

Progress claims

ClaimDateStatusInc GSTOutstanding
PC-01206 Progress Claim 1 - Deposit - 6.5% of Contract4 Oct 2026DRAFT$33,437$33,437
PC-01210 Progress Claim 2 - Site Establishment - 20% of Contract16 Oct 2026DRAFT$102,884$102,884
PC-01214 Progress Claim 3 - Slab / Subfloor Completion - 15% of Contract6 Nov 2026DRAFT$77,163$77,163
PC-01218 Progress Claim 4 - Structural Walls - 10% of Contract27 Nov 2026DRAFT$51,442$51,442
PC-01222 Progress Claim 5 - Roof Cover Stage - 10% of Contract18 Dec 2026DRAFT$51,442$51,442
PC-01226 Progress Claim 6 - Wet Area Tiling - 10% of Contract22 Jan 2027DRAFT$51,442$51,442
PC-01229 Progress Claim 7 - Cabinetry & Stone - 10% of Contract5 Feb 2027DRAFT$51,442$51,442
PC-01232 Progress Claim 8 - Painting & Finishes - 10% of Contract19 Feb 2027DRAFT$51,442$51,442
PC-01235 Progress Claim 9 - Practical Completion - 8.5% of Contract28 Feb 2027DRAFT$43,726$43,726

Variations

VariationStatusEx GST
VO-1102 Contract Adjustment - Agreed Contract Sum $495,000 incl GSTAWAITING_CLIENT_APPROVAL-$17,656

Purchase orders (1)

POSupplierDateStatusEx GSTReceived
PO-03159 59204Termico Certifications1 Sept 2026RECEIVED · APPROVED$400$400

Timesheets (2)

DateWhoHoursTask
2 July 2026Brad Johns1.00Brad Johns - Hawdon Mews costings
8 June 2026Brad Johns2.67Brad Johns - Hillarys job start drawing

Programme (0 items)

ItemStartEnd
Nothing mirrored yet.