ODEION
J-01046 · Large works · 30 Aug 2026 → 1 Aug 2027

43 Monk St - Kensington - Cameron & Rayne - Ext & Ren

Contract (ex GST)
$1,004,058
$1,104,463 inc GST
Variations
$0
Budget (costings)
$775,607
77% of revenue
Committed (POs)
$134,505
17% of budget
Actual cost
$17,973
2% of budget
Claimed (received)
$266,075
26% · $737,982 raised, unpaid

Budget vs committed vs actual, by costing category

CategoryLinesBudgetCommitted (POs)ActualLeft in budgetUsed
L - 1 - Site Set-up / Pickups / Trade Assist / Supervision1$0$0$140-$140
0%
L - Provisional Sums & Allowances (no timesheets)8$14,218$0$0$14,218
0%
L - Site Labour (all Odeion crew hours)8$167,349$0$2,348$165,002
1%
M - 10 - Flooring4$12,726$0$0$12,726
0%
M - 10 - Tiling8$3,091$0$0$3,091
0%
M - 10 - Waterproofing1$3,246$0$0$3,246
0%
M - 11 - Cabinetry - Materials1$47,454$0$0$47,454
0%
M - 11 - Fixing Carpentry9$19,310$0$0$19,310
0%
M - 13 - Appliances10$26,119$0$0$26,119
0%
M - 13 - Bathroom Accessories17$7,918$0$0$7,918
0%
M - 13 - Electrical Selections8$2,437$0$0$2,437
0%
M - 13 - Fittings / Fixtures9$4,447$0$0$4,447
0%
M - 1 - Site Prelims1$10,593$0$0$10,593
0%
M - 3 - Retaining1$6,628$0$0$6,628
0%
M - 4 - Bricklaying3$4,747$0$0$4,747
0%
M - 4 - Concrete1$40,451$0$0$40,451
0%
M - 4 - Internal Door Frames6$1,994$0$0$1,994
0%
M - 4 - Reinforcement / REO1$3,500$0$0$3,500
0%
M - 4 - Structural Steels / Lintels1$213$0$0$213
0%
M - 6 - Framing / Eaves / Hardware4$53,463$0$0$53,463
0%
M - 7 - Roof Cover1$44,683$0$0$44,683
0%
M - 8 - Tapware / Mixers6$1,870$0$0$1,870
0%
M - 9 - Cladding Systems1$34,906$0$0$34,906
0%
M - 9 - Insulation1$3,792$0$0$3,792
0%
*** Phase 1 - Materials1$4,857$0$0$4,857
0%
*** Phase 2 - Materials1$4,857$0$0$4,857
0%
Post Stage – Handover / Maintenance / Warranty1$6,784$0$0$6,784
0%
Pre Stage - Construction Overheads14$43,197$0$12,611$30,587
29%
S - 10 - Glazing3$37,290$0$0$37,290
0%
S - 10 - Tiling1$8,036$0$0$8,036
0%
S - 11 - Cabinetry - Stone1$9,091$0$0$9,091
0%
S - 12 - Concretor (Exposed / Honed / Etc)1$14,137$0$0$14,137
0%
S - 12 - Painting1$14,831$0$0$14,831
0%
S - 13 - Screening & Fencing1$5,631$0$0$5,631
0%
S - 13 - Shower Screens / Mirrors1$1,682$0$0$1,682
0%
S - 13 - Stairs1$1,364$0$0$1,364
0%
S - 14- Final clean1$1,437$0$0$1,437
0%
S - 2 - Air Conditioning (HVAC)2$14,364$0$0$14,364
0%
S - 2 - Electrical6$26,601$0$2,875$23,726
11%
S - 2 - Plumbing5$27,155$0$0$27,155
0%
S - 3 - Hire - Excavator / Bobcat / Pump / Equipment1$4,999$0$0$4,999
0%
S - 4 - Termite Treatments1$2,293$0$0$2,293
0%
S - 5 - Scaffolding1$3,005$0$0$3,005
0%
S - 6 - Fall Protection1$1,317$0$0$1,317
0%
S - 7 - Roof Plumbing1$1,350$0$0$1,350
0%
S - 7 - Windows1$788$0$0$788
0%
S - 9 - Plastering1$25,383$0$0$25,383
0%
POs not linked to a costing line–$0$134,505$0-$134,505
0%
Total$775,607$134,505$17,973$641,101

Wunderbuild vs Xero (supplier bills)

Xero is the ledger. Bills count here when a line is tracked to J-01046 or the bill is linked to one of this job's POs. Read only.

Actual cost, Wunderbuild (ex GST)
$17,973
Bills in Xero (ex GST)
$24,702
$26,529 inc GST · 8 bills
Difference (ex GST)
$6,729
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$10,205
8 bills with no PO link
DateSupplierBillStatusPOEx GSTInc GSTDue
14 Oct 2026PowerFlex Electrical Pty Ltd11334DRAFTnone$1,227$1,350$1,350
14 Oct 2026PowerFlex Electrical Pty Ltd11333DRAFTnone$7,990$8,789$8,789
8 Oct 2026PowerFlex Electrical Pty Ltd11331PAIDnone$2,875$3,162$0
7 Oct 2026Improbuild Pty LtdINV-12661AUTHORISEDnone$60$66$66
30 Sept 2026Surefire Insurance Brokers335476PAIDnone$6,510$7,100$0
29 Sept 2026City of South Perth168794PAIDnone$3,612$3,612$0
25 Sept 2026Construction Training FundINV-392478-T8S0T7PAIDnone$2,209$2,209$0
27 Aug 2026Improbuild Pty LtdINV-12457PAIDnone$220$242$0

Progress claims

ClaimDateStatusInc GSTOutstanding
PC-01205 Progress Claim 1 - Deposit - 6.5% of Contract25 Sept 2026PARTIALLY_RECEIVED$71,790$0
PC-01209 Progress Claim 2 - Site Establishment - 20% of Contract30 Sept 2026RECEIVED$220,893$0
PC-01213 Progress Claim 3 - Slab / Subfloor Completion - 15% of Contract20 Oct 2026DRAFT$165,670$165,670
PC-01217 Progress Claim 4 - Structural Walls - 10% of Contract24 Nov 2026DRAFT$110,446$110,446
PC-01221 Progress Claim 5 - Roof Cover Stage - 10% of Contract19 Dec 2026DRAFT$110,446$110,446
PC-01225 Progress Claim 6 - Wet Area Tiling - 10% of Contract20 Feb 2027DRAFT$110,446$110,446
PC-01228 Progress Claim 7 - Cabinetry & Stone - 10% of Contract20 Mar 2027DRAFT$110,446$110,446
PC-01231 Progress Claim 8 - Painting & Finishes - 10% of Contract24 Apr 2027DRAFT$110,446$110,446
PC-01234 Progress Claim 9 - Practical Completion - 8.5% of Contract27 May 2027DRAFT$93,879$93,879

Variations

VariationStatusEx GST
Nothing mirrored yet.

Purchase orders (13)

POSupplierDateStatusEx GSTReceived
PO-03222 J-01046-CLADDINGBig River Group Pty Ltd14 Oct 2026SENT · NONE$28,885$0
PO-03221 J-01046-FRAMINGBig River Group Pty Ltd14 Oct 2026SENT · NONE$10,249$0
PO-03219 J-01046-PLUMBING-WPWP Services W.A13 Oct 2026SENT · NONE$21,412$0
PO-03188 J-01046-PLUMBINGElexa Plumbing and Gas9 Oct 2026CANCELLED · NONE$18,139$0
PO-03144 J-01046-ELECTRICAL-DISCONNECTPowerFlex Electrical Pty Ltd7 Oct 2026PARTIALLY_RECEIVED · APPROVED$5,750$2,875
PO-03142 J-01046-ELECTRICALPowerFlex Electrical Pty Ltd7 Oct 2026SENT · NONE$31,959$0
PO-03160 INV-12661Improbuild Pty Ltd7 Oct 2026RECEIVED · APPROVED$60$60
PO-03110 J-01046-ASBESTOSAlpha Asbestos Removal3 Oct 2026SENT · NONE$3,046$0
PO-03109 J-01046-ELECTRICAL-SOLARPowerFlex Electrical Pty Ltd3 Oct 2026SENT · NONE$2,455$0
PO-03119 335476Surefire Insurance Brokers30 Sept 2026RECEIVED · APPROVED$6,510$6,510
PO-03043 168794City of South Perth29 Sept 2026RECEIVED · APPROVED$3,612$3,612
PO-03169 INV-392478-T8S0T7Construction Training Fund25 Sept 2026RECEIVED · APPROVED$2,209$2,209
PO-03139 INV-12457Improbuild Pty Ltd27 Aug 2026RECEIVED · APPROVED$220$220

Timesheets (10)

DateWhoHoursTask
17 Oct 2026Jasper Osabofu7.50Monk St - demolition of exterior brick wall (Saturday)
7 Oct 2026Jasper Osabofu1.25Site set-up - temporary fence panels and Odeion banners set out (Doug fitted connectors)
30 Sept 2026Tirrus Lucas2.00Site meeting with Jesse, client and electrician
23 Sept 2026Telaufue Pou2.25Drop off majority of temp fence material.
2 July 2026Brad Johns1.00Brad Johns - Monk St costings
26 June 2026Brad Johns2.75Brad Johns - Kensington cabinetry drawing
25 June 2026Brad Johns6.25Brad Johns - Kensington cabinetry drawing
23 June 2026Brad Johns1.00Brad Johns - Kensington cabinetry drawing
16 June 2026Brad Johns2.50Brad Johns - Kensington cabinetry drawing
29 May 2026Brad Johns2.00Brad Johns - Meeting with client, Kensington

Programme (85 items)

ItemStartEnd
CALL UPS - Stage 0 (order & book - see attached call-up list) (done)31 Aug 202631 Aug 2026
PRE-START - Approvals / HII / Dilapidation / Demo planning (done - site visit 30 Sep)31 Aug 20262 Oct 2026
CALL UPS - Stage 1 (book: fencing, toilet, skips, temp letterbox; temp-power application)5 Oct 20265 Oct 2026
CALL UPS - Stage 2 (book: sparky, plumber, asbestos, temp power, Western Power, earthmover, BYDA)5 Oct 20265 Oct 2026
L - 1 - Site set-up & protection: fencing, toilet, storage zone bed 1, solar bay on side, retained-half protection, key12 Oct 202612 Oct 2026
MATERIAL DELIVERY - M-1 Site prelims: temp fencing, toilet, skip, signage, temp letterbox12 Oct 202612 Oct 2026
L - 2 - Demolish front brick walls, clean & stack bricks (needed to make the new wall match) - started Sat 17 Oct (Jasper)13 Oct 202615 Oct 2026
S - 2 - Electrician - visit A: solar panels off & stored, AC disconnect (unit kept for Cam), NBN provision13 Oct 202613 Oct 2026
S - 2 - Plumber (Warwick, WP Services) - visit A: disconnect wet areas, cap gas at main, tee & cap water main (granny flat stays live), trench gas & water under driveway, dead retic in demo zone - DATE TBC with Warwick14 Oct 202614 Oct 2026
L - 2 - Lift driveway pavers & side wall-bricks (palletise for Cam), clear old soakwell sand & brick piles16 Oct 202619 Oct 2026
MATERIAL DELIVERY - props, temp-frame timber, wrap & tarps for the retained half19 Oct 202619 Oct 2026
L - 2 - Prep cuts: prop retained ridge, cut gable, brick toothing & jarrah cuts, strip ceilings in demo half, temp weather wall, rubble to driveway drop zones20 Oct 202629 Oct 2026
S - 1 - Asbestos - Alpha Asbestos Removal (Dave Mead): licensed removal & clearance certificate (PS - allowance sits in M-11) - BOOKED Wed 21 Oct 7:30am-3pm, clients off site21 Oct 202621 Oct 2026
S - 2 - Electrician - visit B: temp power pole & meter panel (temp-power contractor), granny flat swung to temp supply30 Oct 20262 Nov 2026
S - 1 - Western Power - overhead disconnect (S-2 PS: mains / meter box relocation)2 Nov 20262 Nov 2026
L - 2 - Demo execution: crew with the machine - cut & drop, sort, load out; plumber & sparky on call3 Nov 20265 Nov 2026
CLIENTS OFF SITE - demo days (Cam & Rayne to arrange)3 Nov 20265 Nov 2026
S - 3 - Hire - Excavator (5 t) + bobcat & trucks: DEMO EXECUTION - demo half incl. subfloor & chimneys, load out (earthmover TBC)3 Nov 20265 Nov 2026
L - 2 - Earthworks with the machine: level, fill & compact, set-out pegs off the boundary (house reference is gone)6 Nov 20269 Nov 2026
S - 3 - Hire - Excavator: level & compact demo area, footing trenches, front dig to pool / garden level (earthmover TBC)6 Nov 20269 Nov 2026
CALL UPS - Stage 3 (book: plumber drainage, reo, termite, concrete & pump, engineer inspection, bricks, BNA)6 Nov 20266 Nov 2026
S - 2 - Plumber - visit 1: under-slab drainage, sewer & stormwater connections, soakwell (PS)10 Nov 202612 Nov 2026
MATERIAL DELIVERY - M-4 reo, trench mesh, membrane, bar chairs & formwork13 Nov 202613 Nov 2026
L - 3 - Footings & rear slab: formwork, reo, membrane, pour & finish (57 m2, 6 courses below existing floor)13 Nov 202618 Nov 2026
S - 4 - Termite - slab penetrations, perimeter & cold joints (before the pour)16 Nov 202616 Nov 2026
Footing & slab inspection - engineer (hold point)17 Nov 202617 Nov 2026
MATERIAL DELIVERY - M-4 concrete (footings & slab) + S-3 concrete pump - POUR DAY18 Nov 202618 Nov 2026
CURE HOLD - rear slab (no loads)19 Nov 202623 Nov 2026
MATERIAL DELIVERY - M-4/M-5 face bricks (PC - salvaged bricks first), steel lintels, sand & cement20 Nov 202620 Nov 2026
CALL UPS - Stage 4 (book: timber & LVL, trestles, fall protection, glazier measure, engineer frame inspection)24 Nov 202624 Nov 2026