J-01045 · Large works · 23 Aug 2026 → 8 July 2027
7 Turriff Rd - Floreat - Catherine & Deepak - Ext & Ren
Contract (ex GST)
$949,914
$1,044,906 inc GST
Variations
-$99,826
Budget (costings)
$635,432
75% of revenue
Committed (POs)
$210,726
33% of budget
Actual cost
$68,118
11% of budget
Claimed (received)
$394,214
46% · $455,874 raised, unpaid
Budget vs committed vs actual, by costing category
| Category | Lines | Budget | Committed (POs) | Actual | Left in budget | Used |
|---|---|---|---|---|---|---|
| Internal Charge 01001 | 3 | $0 | $0 | $0 | $0 | 0% |
| L - Cabinetry Labour (Brad) | 1 | $7,386 | $0 | $0 | $7,386 | 0% |
| L - Provisional Sums & Allowances (no timesheets) | 13 | $49,942 | $0 | $7,950 | $41,992 | 16% |
| L - Site Labour (all Odeion crew hours) | 7 | $170,798 | $0 | $28,714 | $142,084 | 17% |
| M - 10 - Waterproofing | 1 | $10,432 | $0 | $0 | $10,432 | 0% |
| M - 11 - Cabinetry - Materials | 1 | $11,078 | $0 | $0 | $11,078 | 0% |
| M - 11 - Fixing Carpentry | 1 | $5,245 | $0 | $0 | $5,245 | 0% |
| M - 13 - Appliances | 3 | $3,982 | $0 | $0 | $3,982 | 0% |
| M - 13 - Bathroom Accessories | 26 | $8,980 | $0 | $0 | $8,980 | 0% |
| M - 13 - Electrical Selections | 1 | $1,818 | $0 | $0 | $1,818 | 0% |
| M - 13 - Fittings / Fixtures | 1 | $182 | $0 | $0 | $182 | 0% |
| M - 1 - Site Prelims | 3 | $12,385 | $0 | $6,706 | $5,679 | 54% |
| M - 3 - Retaining | 1 | $7,800 | $0 | $0 | $7,800 | 0% |
| M - 4 - Bricklaying | 1 | $3,595 | $0 | $1,295 | $2,299 | 36% |
| M - 4 - Concrete | 1 | $7,906 | $0 | $946 | $6,960 | 12% |
| M - 4 - Reinforcement / REO | 1 | $720 | $0 | $0 | $720 | 0% |
| M - 4 - Structural Steels / Lintels | 2 | $18,182 | $0 | $0 | $18,182 | 0% |
| M - 6 - Framing / Eaves / Hardware | 1 | $39,932 | $0 | $5,198 | $34,734 | 13% |
| M - 7 - Roof Cover | 1 | $44,249 | $0 | $0 | $44,249 | 0% |
| M - 7 - Roof Plumbing | 1 | $2,694 | $0 | $0 | $2,694 | 0% |
| M - 8 - Tapware / Mixers | 7 | $1,875 | $0 | $0 | $1,875 | 0% |
| M - 9 - Cladding Systems | 1 | $4,053 | $0 | $0 | $4,053 | 0% |
| M - 9 - Insulation | 1 | $4,643 | $0 | $0 | $4,643 | 0% |
| M - 9 - Rendering | 1 | $5,687 | $0 | $0 | $5,687 | 0% |
| Odeion Contribution | 1 | -$99,826 | $0 | $0 | -$99,826 | 0% |
| *** Phase 1 - Materials | 1 | $4,593 | $0 | $0 | $4,593 | 0% |
| *** Phase 2 - Materials | 1 | $4,593 | $0 | $0 | $4,593 | 0% |
| Post Stage – Handover / Maintenance / Warranty | 1 | $6,409 | $0 | $0 | $6,409 | 0% |
| Pre Stage - Construction Overheads | 13 | $33,878 | $0 | $7,479 | $26,399 | 22% |
| S - 10 - Flooring | 6 | $15,284 | $0 | $0 | $15,284 | 0% |
| S - 10 - Glazing | 3 | $36,998 | $0 | $0 | $36,998 | 0% |
| S - 10 - Tiling | 14 | $10,784 | $0 | $0 | $10,784 | 0% |
| S - 11 - Cabinetry - Stone | 1 | $6,155 | $0 | $0 | $6,155 | 0% |
| S - 12 - Painting | 1 | $29,968 | $0 | $0 | $29,968 | 0% |
| S - 13 - Balustrades / Handrails | 4 | $19,875 | $0 | $0 | $19,875 | 0% |
| S - 13 - Shower Screens / Mirrors | 4 | $5,182 | $0 | $0 | $5,182 | 0% |
| S - 13 - Stairs | 4 | $24,946 | $0 | $0 | $24,946 | 0% |
| S - 14 - Final clean | 1 | $2,563 | $0 | $0 | $2,563 | 0% |
| S - 2 - Air Conditioning (HVAC) | 2 | $7,273 | $0 | $0 | $7,273 | 0% |
| S - 2 - Electrical | 7 | $22,867 | $0 | $5,622 | $17,246 | 25% |
| S - 2 - Plumbing | 1 | $21,507 | $0 | $209 | $21,299 | 1% |
| S - 3 - Excavator / Bobcat | 3 | $5,158 | $0 | $3,600 | $1,558 | 70% |
| S - 4 - Concrete Pumping | 1 | $320 | $0 | $0 | $320 | 0% |
| S - 4 - Termite Treatments | 1 | $630 | $0 | $400 | $230 | 64% |
| S - 5 - Crane Hire / Dogman | 1 | $1,564 | $0 | $0 | $1,564 | 0% |
| S - 5 - Scaffolding | 1 | $14,762 | $0 | $0 | $14,762 | 0% |
| S - 6 - Fall Protection | 1 | $3,456 | $0 | $0 | $3,456 | 0% |
| S - 7 - Windows | 1 | $2,253 | $0 | $0 | $2,253 | 0% |
| S - 9 - Plastering | 1 | $26,898 | $0 | $0 | $26,898 | 0% |
| S - 9 - Rendering | 1 | $3,782 | $0 | $0 | $3,782 | 0% |
| POs not linked to a costing line | – | $0 | $210,726 | $0 | -$210,726 | 0% |
| Total | $635,432 | $210,726 | $68,118 | $424,707 |
Wunderbuild vs Xero (supplier bills)
Xero is the ledger. Bills count here when a line is tracked to J-01045 or the bill is linked to one of this job's POs. Read only.
Actual cost, Wunderbuild (ex GST)
$68,118
Bills in Xero (ex GST)
$65,036
$70,976 inc GST · 47 bills
Difference (ex GST)
-$3,082
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$34,074
47 bills with no PO link
| Date | Supplier | Bill | Status | PO | Ex GST | Inc GST | Due |
|---|---|---|---|---|---|---|---|
| 16 Oct 2026 | Big River Group Pty Ltd | 602-1473950 | DRAFT | none | $6,115 | $6,727 | $6,727 |
| 16 Oct 2026 | Big River Group Pty Ltd | 602-1473380 | DRAFT | none | $4,571 | $5,029 | $5,029 |
| 15 Oct 2026 | Big River Group Pty Ltd | 602-1473406 | AUTHORISED | none | $9,122 | $10,034 | $10,034 |
| 12 Oct 2026 | Big River Group Pty Ltd | 602-1483653 | AUTHORISED | none | $126 | $139 | $139 |
| 12 Oct 2026 | Big River Group Pty Ltd | 602-1483287 | AUTHORISED | none | $680 | $748 | $748 |
| 8 Oct 2026 | Bunnings Group Limited | 2404/01324961 | AUTHORISED | none | $470 | $517 | $517 |
| 7 Oct 2026 | Improbuild Pty Ltd | INV-12688 | AUTHORISED | none | $420 | $462 | $462 |
| 30 Sept 2026 | Instant Products Hire | 238779 | AUTHORISED | none | $225 | $248 | $248 |
| 30 Sept 2026 | Instant Waste Management | 5231984 | AUTHORISED | none | $2,993 | $3,292 | $3,292 |
| 24 Sept 2026 | Atco Gas Australia | 1800037664 | PAID | none | $209 | $209 | $0 |
| 24 Sept 2026 | Holcim Australia | 9410572599 | AUTHORISED | none | $302 | $333 | $333 |
| 23 Sept 2026 | Bunnings Group Limited | 2404/01316990 | AUTHORISED | none | $28 | $31 | $31 |
| 23 Sept 2026 | Bunnings Group Limited | 2404/01316986 | AUTHORISED | none | $72 | $80 | $80 |
| 22 Sept 2026 | Termico Certifications | 59207 | AUTHORISED | none | $400 | $440 | $440 |
| 22 Sept 2026 | Big River Group Pty Ltd | 602-1471431 | AUTHORISED | none | $1,500 | $1,650 | $1,650 |
| 21 Sept 2026 | PowerFlex Electrical Pty Ltd | 11322 | PAID | none | $3,167 | $3,484 | $0 |
| 21 Sept 2026 | Bunnings Group Limited | 2404/01315752 | AUTHORISED | none | $46 | $51 | $51 |
| 18 Sept 2026 | Holcim Australia | 9410563648 | AUTHORISED | none | $644 | $708 | $708 |
| 17 Sept 2026 | Bunnings Group Limited | 2404/01313730 | AUTHORISED | none | $24 | $27 | $27 |
| 16 Sept 2026 | PowerFlex Electrical Pty Ltd | 11319 | PAID | none | $2,455 | $2,700 | $0 |
| 16 Sept 2026 | Bunnings Group Limited | 2260/91017019 | AUTHORISED | none | $108 | $118 | $118 |
| 15 Sept 2026 | Big River Group Pty Ltd | 602-1462529 | AUTHORISED | none | $2,357 | $2,593 | $2,593 |
| 14 Sept 2026 | Bunnings Group Limited | 2404/01312123 | AUTHORISED | none | $36 | $40 | $40 |
| 14 Sept 2026 | Bunnings Group Limited | 2404/01312166 | AUTHORISED | none | $4 | $4 | $4 |
| 14 Sept 2026 | Bunnings Group Limited | 2404/01312501 | AUTHORISED | none | $104 | $115 | $115 |
| 11 Sept 2026 | Bunnings Group Limited | 2404/01310740 | AUTHORISED | none | $253 | $279 | $279 |
| 11 Sept 2026 | Bunnings Group Limited | 2404/01310931 | AUTHORISED | none | $111 | $122 | $122 |
| 10 Sept 2026 | Bunnings Group Limited | 2404/00181572 | AUTHORISED | none | $264 | $290 | $290 |
| 8 Sept 2026 | BA & CB Wright Transport Pty Ltd | PAID | none | $1,249 | $1,374 | $0 | |
| 3 Sept 2026 | Leading Energy ESD | 258234 | PAID | none | $650 | $715 | $0 |
| 31 Aug 2026 | Instant Waste Management | 5221890 | PAID | none | $156 | $172 | $0 |
| 31 Aug 2026 | Instant Products Hire | 236526 | PAID | none | $158 | $174 | $0 |
| 20 Aug 2026 | Australian Building Specialist | INV-21227600 | PAID | none | $200 | $220 | $0 |
| 31 July 2026 | Instant Products Hire | 233915 | PAID | none | $230 | $253 | $0 |
| 17 July 2026 | Improbuild Pty Ltd | INV-12056 | PAID | none | $100 | $110 | $0 |
| 1 July 2026 | MetWest Steel | 826308 | PAID | none | $4,033 | $4,436 | $0 |
| 1 July 2026 | Termico Certifications | 57157 | PAID | none | $400 | $440 | $0 |
| 1 July 2026 | Instant Waste Management | 5201781 | PAID | none | $655 | $721 | $0 |
| 30 June 2026 | Instant Products Hire | 232346 | PAID | none | $395 | $435 | $0 |
| 22 June 2026 | Improbuild | INV-11914 | PAID | none | $285 | $314 | $0 |
| 12 June 2026 | Aftermath Limestone & Fencing | INV-0290 | PAID | none | $7,950 | $8,745 | $0 |
| 10 June 2026 | Site HQ | INV-106636 | PAID | none | $1,704 | $1,874 | $0 |
| 9 June 2026 | ABC Containers | ABC3206 | PAID | none | $300 | $330 | $0 |
| 9 June 2026 | Savvy Stump Grinding and Tree Services Pty Ltd | INV-0190 | PAID | none | $300 | $330 | $0 |
| 9 June 2026 | Davis Transport & Earthworks | INV-0361 | PAID | none | $3,600 | $3,960 | $0 |
| 5 June 2026 | Town of Cambridge | PAID | none | $5,424 | $5,424 | $0 | |
| 27 May 2026 | BA & CB Wright Transport Pty Ltd | 7255 | PAID | none | $440 | $484 | $0 |
Progress claims
| Claim | Date | Status | Inc GST | Outstanding |
|---|---|---|---|---|
| PC-01180 Progress Claim 1 - Deposit - 6.5% of Contract | 28 May 2026 | SENT | $67,919 | $67,919 |
| PC-01181 Progress Claim 2 - Site Establishment - 20% of Contract | 9 June 2026 | SENT | $208,981 | $208,981 |
| PC-01184 Progress Claim 5 - Roof Cover Stage - 10% of Contract | 13 Aug 2026 | DRAFT | $85,720 | $85,720 |
| PC-01185 Progress Claim 6 - Wet Area Tiling - 10% of Contract | 13 Aug 2026 | DRAFT | $85,720 | $85,720 |
| PC-01186 Progress Claim 7 - Cabinetry & Stone - 10% of Contract | 13 Aug 2026 | DRAFT | $85,720 | $85,720 |
| PC-01188 Progress Claim 9 - Practical Completion - 8.5% of Contract | 13 Aug 2026 | DRAFT | $72,862 | $72,862 |
| PC-01187 Progress Claim 8 - Painting & Finishes - 10% of Contract | 13 Aug 2026 | DRAFT | $85,720 | $85,720 |
| PC-01183 Progress Claim 4 - Structural Walls - 10% of Contract | 13 Aug 2026 | DRAFT | $85,720 | $85,720 |
| PC-01182 Progress Claim 3 - Slab / Subfloor Completion - 15% of Contract | 23 Sept 2026 | RECEIVED | $156,736 | $0 |
Variations
| Variation | Status | Ex GST |
|---|---|---|
| VO-1098 Odeion Contribution - Redesign Credit | APPROVED_BY_BUILDER | -$99,826 |
Purchase orders (48)
| PO | Supplier | Date | Status | Ex GST | Received |
|---|---|---|---|---|---|
| PO-03200 602-1483653 | Big River Group Pty Ltd | 12 Oct 2026 | RECEIVED · APPROVED | $126 | $126 |
| PO-03199 602-1483287 | Big River Group Pty Ltd | 12 Oct 2026 | RECEIVED · APPROVED | $680 | $680 |
| PO-03202 2404/01324961 | Bunnings Group Limited | 8 Oct 2026 | RECEIVED · APPROVED | $470 | $470 |
| PO-03161 INV-12688 | Improbuild Pty Ltd | 7 Oct 2026 | RECEIVED · APPROVED | $420 | $420 |
| PO-03184 INV-0052 | BuiltEco | 6 Oct 2026 | RECEIVED · APPROVED | $1,920 | $1,920 |
| PO-03107 J-01045-FRAMING | Big River Group Pty Ltd | 2 Oct 2026 | SENT · NONE | $35,313 | $0 |
| PO-03079 J-01045-SCAFFOLD | West Coast Scaffolding | 1 Oct 2026 | SENT · NONE | $13,286 | $0 |
| PO-03078 J-01045-ELECTRICAL | PowerFlex Electrical Pty Ltd | 1 Oct 2026 | PARTIALLY_RECEIVED · APPROVED | $13,381 | $3,167 |
| PO-03076 J-01045-BRICKLAYING | BNA Bricklaying | 1 Oct 2026 | SENT · NONE | $2,655 | $0 |
| PO-03082 J-01045-PAINTING | LA Painting & Decorating | 1 Oct 2026 | SENT · NONE | $26,970 | $0 |
| PO-03077 J-01045-PLUMBING | WP Services W.A | 1 Oct 2026 | SENT · NONE | $16,632 | $0 |
| PO-03081 J-01045-PLASTERING | Emberforge Pty Ltd | 1 Oct 2026 | SENT · NONE | $24,208 | $0 |
| PO-03080 J-01045-ROOFING | Jacobson Roofing | 1 Oct 2026 | SENT · NONE | $39,824 | $0 |
| PO-03147 5231984 | Instant Waste Management | 30 Sept 2026 | RECEIVED · APPROVED | $2,993 | $2,993 |
| PO-03114 238779 | Instant Products Hire | 30 Sept 2026 | RECEIVED · APPROVED | $225 | $225 |
| PO-03171 1800037664 | Atco Gas Australia | 24 Sept 2026 | RECEIVED · APPROVED | $209 | $209 |
| PO-03053 9410572599 | Holcim Australia | 24 Sept 2026 | RECEIVED · APPROVED | $302 | $302 |
| PO-03056 2404/01316986 | Bunnings Group Limited | 23 Sept 2026 | RECEIVED · APPROVED | $72 | $72 |
| PO-03057 2404/01316990 | Bunnings Group Limited | 23 Sept 2026 | RECEIVED · APPROVED | $28 | $28 |
| PO-03157 59207 | Termico Certifications | 22 Sept 2026 | RECEIVED · APPROVED | $400 | $400 |
| PO-03054 602-1471431 | Big River Group Pty Ltd | 22 Sept 2026 | RECEIVED · APPROVED | $1,500 | $1,500 |
| PO-03055 2404/01315752 | Bunnings Group Limited | 21 Sept 2026 | RECEIVED · APPROVED | $46 | $46 |
| PO-03052 9410563648 | Holcim Australia | 18 Sept 2026 | RECEIVED · APPROVED | $644 | $644 |
| PO-03027 2404/01313730 | Bunnings Group Limited | 17 Sept 2026 | RECEIVED · APPROVED | $24 | $24 |
| PO-02813 11319 | PowerFlex Electrical Pty Ltd | 16 Sept 2026 | RECEIVED · APPROVED | $2,455 | $2,455 |
| PO-03026 2260/91017019 | Bunnings Group Limited | 16 Sept 2026 | RECEIVED · APPROVED | $108 | $108 |
| PO-02806 602-1462529 | Big River Group Pty Ltd | 15 Sept 2026 | RECEIVED · APPROVED | $2,357 | $2,357 |
| PO-03023 2404/01312123 | Bunnings Group Limited | 14 Sept 2026 | RECEIVED · APPROVED | $36 | $36 |
| PO-03024 2404/01312501 | Bunnings Group Limited | 14 Sept 2026 | RECEIVED · APPROVED | $104 | $104 |
| PO-03025 2404/01312166 | Bunnings Group Limited | 14 Sept 2026 | RECEIVED · APPROVED | $4 | $4 |
| PO-02794 2404/01310931 | Bunnings Group Limited | 11 Sept 2026 | RECEIVED · APPROVED | $111 | $111 |
| PO-02797 2404/01310740 | Bunnings Group Limited | 11 Sept 2026 | RECEIVED · APPROVED | $253 | $253 |
| PO-02805 2404/00181572 | Bunnings Group Limited | 10 Sept 2026 | RECEIVED · APPROVED | $264 | $264 |
| PO-02807 No reference | BA & CB Wright Transport Pty Ltd | 8 Sept 2026 | RECEIVED · APPROVED | $1,249 | $1,249 |
| PO-02814 258234 | Leading Energy ESD | 3 Sept 2026 | RECEIVED · APPROVED | $650 | $650 |
| PO-02786 5221890 | Instant Waste Management | 31 Aug 2026 | RECEIVED · APPROVED | $156 | $156 |
| PO-03201 236526 | Instant Products Hire | 31 Aug 2026 | RECEIVED · APPROVED | $158 | $158 |
| PO-02815 INV-21227600 | Australian Building Specialist | 20 Aug 2026 | RECEIVED · APPROVED | $200 | $200 |
| PO-02789 233915 | Instant Products Hire | 31 July 2026 | RECEIVED · APPROVED | $230 | $230 |
| PO-03138 INV-12056 | Improbuild Pty Ltd | 17 July 2026 | RECEIVED · APPROVED | $100 | $100 |
| PO-02712 57157 | Termico Certifications | 1 July 2026 | RECEIVED · APPROVED | $400 | $400 |
| PO-02719 INV-11914 | Improbuild | 22 June 2026 | RECEIVED · APPROVED | $285 | $285 |
| PO-02718 INV-0290 | Aftermath Limestone & Fencing | 12 June 2026 | RECEIVED · APPROVED | $7,950 | $7,950 |
| PO-02714 INV-106636 | Site HQ | 10 June 2026 | RECEIVED · APPROVED | $1,704 | $1,704 |
| PO-02716 ABC3206 | ABC Containers | 9 June 2026 | RECEIVED · APPROVED | $300 | $300 |
| PO-02713 INV-0361 | Davis Transport & Earthworks | 9 June 2026 | RECEIVED · APPROVED | $3,600 | $3,600 |
| PO-02715 INV-0190 | Savvy Stump Grinding and Tree Services Pty Ltd | 9 June 2026 | RECEIVED · APPROVED | $300 | $300 |
| PO-02717 No reference | Town of Cambridge | 5 June 2026 | RECEIVED · APPROVED | $5,424 | $5,424 |
Timesheets (87)
| Date | Who | Hours | Task |
|---|---|---|---|
| 16 Oct 2026 | Jordan Greenhill | 7.50 | Turriff - ceilings and walls with Kristian & Nathan |
| 16 Oct 2026 | Nathan Lake | 3.50 | 4. Framing (walls, floor, roof, eaves & fascia) |
| 16 Oct 2026 | Kristian Yates | 6.00 | Turriff - remove section of roof/ceiling, adjust wall plates, plumb walls, site meeting, screw studs to plates |
| 16 Oct 2026 | Jasper Osabofu | 1.25 | Turriff - drop materials, small amount of asbestos, empty ute rubbish |
| 16 Oct 2026 | Kristian Yates | 2.00 | Turriff - site clean and stack timbers |
| 15 Oct 2026 | Jordan Greenhill | 8.00 | Turriff - wall framing, floor noggins, ceiling joists (with Kristian) |
| 15 Oct 2026 | Kristian Yates | 8.00 | Turriff - wall framing, floor noggins, ceiling joists (with Jordan) |
| 14 Oct 2026 | Jordan Greenhill | 8.00 | Turriff - first floor wall frames (with Kristian) |
| 14 Oct 2026 | Kristian Yates | 8.00 | Turriff - wall framing with Jordan |
| 13 Oct 2026 | Kristian Yates | 1.00 | Turriff - Bunnings run for nails |
| 13 Oct 2026 | Jordan Greenhill | 8.00 | Turriff - first floor wall frames |
| 13 Oct 2026 | Kristian Yates | 3.50 | Turriff - wall framing with Jordan |
| 12 Oct 2026 | Jordan Greenhill | 4.00 | Turriff - framing timber pickup |
| 12 Oct 2026 | Jordan Greenhill | 4.00 | Turriff - first floor wall frames: unload timber, drop saw set-up, cut all studs to 3104 |
| 10 Oct 2026 | Jordan Greenhill | 5.00 | Turriff - first floor subfloor: plane timbers level, platform for stud walls (Saturday) |
| 9 Oct 2026 | Jordan Greenhill | 8.00 | Framing - marking out wall frames, full day solo. About 2 days to go |
| 8 Oct 2026 | Jordan Greenhill | 4.00 | Framing - finishing the subfloor (solo) |
| 8 Oct 2026 | Jordan Greenhill | 2.50 | Framing - started on wall frames (solo) |
| 7 Oct 2026 | Jordan Greenhill | 3.00 | Demolition - moved bricks (1.5h), levelled sand (1h), moved steels, top plates off walls |
| 6 Oct 2026 | Jordan Greenhill | 2.50 | Site clean (1h) and container clean & organise (1.5h) |
| 6 Oct 2026 | Jordan Greenhill | 5.75 | Demolition - trees out by the front stairs (3h), jackhammer bathroom screed (2h), bricks to the front (40m), prop timber bagged to bearers (10m) |
| 5 Oct 2026 | Jordan Greenhill | 7.75 | Demolition - wet saw cuts, squared walls for stud walls, taking down front of house |
| 3 Oct 2026 | Jasper Osabofu | 1.25 | Demolition - knocking bricks off a wall; unloaded the Glenbank materials with Jordan |
| 3 Oct 2026 | Jordan Greenhill | 1.50 | Demolition |
| 2 Oct 2026 | Jasper Osabofu | 1.33 | Pickups - unloaded Glenbank cladding, doors, cabinetry, scaffold at Turriff with Jordan; helped move jarrah pile |
| 2 Oct 2026 | Jordan Greenhill | 7.75 | Demolition - sorted jarrah into piles, stripped roof by front door, started bringing down back-right master bedroom roof |
| 2 Oct 2026 | Telaufue Pou | 1.33 | Met Jasper at Jesses place. To unload ute and trailee at Turriff Rd. After unloading, we helped Jordan move Jarrah from roof and floor demo to better spot. |
| 1 Oct 2026 | Jordan Greenhill | 7.75 | Demolition - stripped all jarrah and battens off the roof, ceiling taken down (pile by the bin to tidy). Roof and ceiling strip finished. |
| 1 Oct 2026 | Jasper Osabofu | 3.00 | Pickups for Turriff - collected ute and trailer from Cambridge Way, loaded scaffold, cladding and 2 doors at Glenbank for delivery to Turriff next morning |
| 30 Sept 2026 | Jordan Greenhill | 7.75 | Demolition - bathroom floor tiles (3 hrs) and roof tiles stripped over the extension area (4 hrs). Roof tiles finished. |
Programme (65 items)
| Item | Start | End |
|---|---|---|
| L - 1 - Site set-up & protection (done) | 14 Sept 2026 | 18 Sept 2026 |
| L - 2 - Demolition - external & strip-out (done, ~half of all demo) | 15 Sept 2026 | 25 Sept 2026 |
| Electrician - disconnect & make safe, solar removal (done) | 15 Sept 2026 | 15 Sept 2026 |
| Earthworks - bulk excavation & site levels (done) | 15 Sept 2026 | 16 Sept 2026 |
| L - 3 - Footings - GF extension (done) | 18 Sept 2026 | 18 Sept 2026 |
| Bricklayer - brickwork to subfloor height (done) | 21 Sept 2026 | 21 Sept 2026 |
| L - 4 - GF extension subfloor (done) | 22 Sept 2026 | 23 Sept 2026 |
| L - 2 - Internal demolition (remaining half) | 28 Sept 2026 | 9 Oct 2026 |
| L - 4 - GF extension external timber walls | 5 Oct 2026 | 6 Oct 2026 |
| L - 4 - GF extension ceiling frame | 7 Oct 2026 | 7 Oct 2026 |
| Electrician - supply & set new meter box for brick-in (PS) | 7 Oct 2026 | 7 Oct 2026 |
| MATERIAL DELIVERY - bricks, sand, cement & lintels for outer skin | 7 Oct 2026 | 7 Oct 2026 |
| Bricklayer - external skin to plate height | 8 Oct 2026 | 9 Oct 2026 |
| L - 4 - Random framing works | 8 Oct 2026 | 9 Oct 2026 |
| Western Power - disconnect / reconnect (TO BOOK - date placeholder) | 9 Oct 2026 | 9 Oct 2026 |
| Scaffolder - erect full perimeter + stair-void scaffold | 12 Oct 2026 | 12 Oct 2026 |
| Crane hire / dogman - structural steel lift | 13 Oct 2026 | 13 Oct 2026 |
| L - 4 - Structural steel install - GF & FF posts & beams (steel on site) | 13 Oct 2026 | 19 Oct 2026 |
| Material delivery order 1 - Ground floor walls and floor sheathing, Ground floor roof, First floor floor sub-framing | 19 Oct 2026 | 19 Oct 2026 |
| L - 4 - First floor subfloor - bearers, LVL joists & sheeting | 20 Oct 2026 | 26 Oct 2026 |
| L - 4 - First floor wall frames | 27 Oct 2026 | 2 Nov 2026 |
| Big River material order 2 (DELIVERY DATE TBC) - FF walls, FF roof, external decking & decking subfloor | 30 Oct 2026 | 30 Oct 2026 |
| Fall / edge protection hire - install, hire period & removal | 3 Nov 2026 | 11 Nov 2026 |
| L - 4 - Roof frame, eaves & fascia | 3 Nov 2026 | 11 Nov 2026 |
| MATERIAL DELIVERY - roof plumbing (downpipes & fittings) | 12 Nov 2026 | 12 Nov 2026 |
| Frame inspection (hold point) | 12 Nov 2026 | 12 Nov 2026 |
| Roofer - roof sheeting, gutters & downpipes | 13 Nov 2026 | 19 Nov 2026 |
| MATERIAL DELIVERY - Greenboard cladding, wrap & trims | 19 Nov 2026 | 19 Nov 2026 |
| MATERIAL DELIVERY - Harvey Norman Commercial order 1: mixer bodies & in-wall items (Duncan) | 19 Nov 2026 | 19 Nov 2026 |
| Plumber - rough-in | 20 Nov 2026 | 24 Nov 2026 |