J-01035 · Large works · 15 Mar 2026 → 7 June 2026

3 Valley Close - Canning Vale - Metta & Ayden - Ext & Ren

Contract (ex GST)
$391,690
$430,859 inc GST
Variations
-$42,367
Budget (costings)
$266,556
76% of revenue
Committed (POs)
$161,967
61% of budget
Actual cost
$222,969
84% of budget
Claimed (received)
$349,323
100% · $0 raised, unpaid

Budget vs committed vs actual, by costing category

CategoryLinesBudgetCommitted (POs)ActualLeft in budgetUsed
L - 11 - Cabinetry / Fixout1$1,531$0$1,450$81
95%
L - 14 - Detailing / QA / Handover2$1,280$0$1,175$105
92%
L - 1 - Site Works / Temporary Services2$7,449$0$4,930$2,519
66%
L - 2 - Demolition / Disconnections1$5,120$0$2,658$2,463
52%
L - 3 - Earthworks / Drainage / Retaining1$1,120$0$4,290-$3,170
383%
L - 4 - Formwork / Concrete2$3,926$0$3,545$381
90%
L - 5 - Wall Construction / Subfloor Framing2$9,976$0$9,752$223
98%
L - 6 - Ceiling Frame / Roof Frame2$17,287$0$12,790$4,497
74%
L - 8 - Rough-In Services / External Envelope1$0$0$1,148-$1,148
0%
L - 9 - Linings / Render1$4,243$0$2,542$1,701
60%
M - 10 - Tiling8$0$0$4,197-$4,197
642075016983170600%
M - 11 - Cabinetry4$5,273$0$7,535-$2,262
143%
M - 11 - Fixing Carpentry2$2,705$0$5,861-$3,157
217%
M - 1 - Site Prelims3$6,502$0$7,006-$505
108%
M - 3 - Retaining3$4,784$0$4,784$0
100%
M - 3 - Site Drainage / Stormwater1$727$0$3,630-$2,902
499%
M - 4 - Bricklaying1$3,208$0$570$2,638
18%
M - 4 - Reinforcement / REO1$2,523$0$642$1,881
25%
M - 6 - Framing / Eaves / Hardware1$11,553$0$12,398-$845
107%
M - 9 - Cladding Systems5$1,026$0$3,366-$2,340
328%
*** Phase 1 - Materials1$1,920$0$925$995
48%
*** Phase 1 - Odeion Labour (Supervision)1$4,500$0$4,738-$238
105%
*** Phase 2 - Materials1$1,920$0$0$1,920
0%
*** Phase 2 - Odeion Labour (Supervision)1$4,500$0$6,894-$2,394
153%
Post Stage – Handover / Maintenance / Warranty1$2,948$0$1,325$1,623
45%
Pre Stage - Construction Overheads2$16,629$0$1,138$15,491
7%
S - 10 - Tiling4$21,696$0$1,000$20,696
5%
S - 11- Stone Mason4$0$0$0$0
0%
S - 12 - Concretor (Exposed / Honed / Etc)3$22,162$0$11,538$10,624
52%
S - 12 - Painting5$9,211$0$5,558$3,653
60%
S - 12 - Paving1$1,818$0$0$1,818
0%
S - 1 - Asbestos Contractor1$4,545$0$850$3,695
19%
S - 2 - Air Conditioning (HVAC)4-$0$0$0-$0
0%
S - 2 - Electrical5$5,165$0$11,371-$6,205
220%
S - 3 - Excavator / Bobcat1$1,909$0$0$1,909
0%
S - 4 - Concrete Pumping1$2,881$0$0$2,881
0%
S - 4 - Termite Treatments1$714$0$1,400-$686
196%
S - 5 - Scaffolding1$4,731$0$0$4,731
0%
S - 7 - Roof Plumbing1$47,146$0$33,016$14,130
70%
S - 7 - Windows1$17,402$0$26,370-$8,968
152%
S - 9 - Plastering2$10,309$0$22,510-$12,201
218%
Variation 010881-$12,395$0$0-$12,395
0%
Variation 010901$9,300$0$69$9,231
1%
Variation 010941-$1,250$0$0-$1,250
0%
Variation 010951-$1,440$0$0-$1,440
0%
POs not linked to a costing line–$0$161,967$0-$161,967
0%
Total$266,556$161,967$222,969$43,587

Wunderbuild vs Xero (supplier bills)

Xero is the ledger. Bills count here when a line is tracked to J-01035 or the bill is linked to one of this job's POs. Read only.

Actual cost, Wunderbuild (ex GST)
$222,969
Bills in Xero (ex GST)
$152,720
$167,390 inc GST · 95 bills
Difference (ex GST)
-$70,249
Xero minus Wunderbuild
Unpaid in Xero (inc GST)
$0
95 bills with no PO link
DateSupplierBillStatusPOEx GSTInc GSTDue
31 Aug 2026Instant Waste Management5221887PAIDnone$138$152$0
24 Aug 2026Instant Products Hire235152PAIDnone$321$353$0
24 Aug 2026Hua LuanINV-0531PAIDnone$1,450$1,595$0
4 Aug 2026PBM PowerINV-3347PAIDnone$745$820$0
4 Aug 2026Bunnings Group Limited2016/01332826PAIDnone$27$29$0
31 July 2026Bunnings Group Limited2435/01380957PAIDnone$46$50$0
31 July 2026Instant Waste Management5211824PAIDnone$12$13$0
31 July 2026Instant Products Hire233912PAIDnone$292$322$0
31 July 2026Bunnings Group Limited2016/01328497PAIDnone$16$18$0
31 July 2026Bunnings Group Limited2206/00741247PAIDnone$56$61$0
29 July 2026Bunnings Group Limited2016/01589746PAIDnone$201$221$0
29 July 2026Bunnings Group Limited2435/01484410PAIDnone$19$21$0
28 July 2026Versatile Building Products10097891PAIDnone$60$66$0
28 July 2026Bunnings Group Limited2016/01325521PAIDnone$72$79$0
15 July 2026Cut2Trade Pty LtdPAIDnone$69$76$0
8 July 2026Bunnings Group Limited2016/01581375PAIDnone$103$113$0
6 July 2026Perfect Glaze Australia Pty Ltd1886PAIDnone$120$132$0
2 July 2026Aspect Decor PaintingINV-1278PAIDnone$1,691$1,860$0
1 July 2026Instant Waste Management5201779PAIDnone$655$721$0
30 June 2026Instant Products Hire232343PAIDnone$225$248$0
29 June 2026Bunnings Group Limited2016/01577635PAIDnone$110$121$0
24 June 2026Decorar Concrete SolutionsINV-0573PAIDnone$10,088$11,097$0
17 June 2026Bunnings Group Limited2206/00791606PAIDnone$130$143$0
17 June 2026Bunnings Group Limited2443/01467230PAIDnone$347$382$0
16 June 2026Peter RandallINV-20260616PAIDnone$900$900$0
11 June 2026Bunnings Group Limited2016/01570328PAIDnone$134$148$0
9 June 2026Bunnings Group Limited2016/01569510PAIDnone$33$37$0
9 June 2026InStyle LacquerINV-0819PAIDnone$2,507$2,757$0
8 June 2026Bunnings Group Limited2016/01569108PAIDnone$65$71$0
8 June 2026BNA Bricklaying1634PAIDnone$1,788$1,966$0
4 June 2026Bunnings Group Limited2016/01370375PAIDnone$22$24$0
3 June 2026Bunnings Group Limited2016/01567136PAIDnone$18$20$0
2 June 2026Cushions & Covers2334PAIDnone$177$195$0
2 June 2026Bunnings Group Limited2016/01368525PAIDnone$78$86$0
31 May 2026Instant Waste Management5191789PAIDnone$674$742$0
31 May 2026Instant Products Hire229776PAIDnone$221$243$0
30 May 2026Peter RandallINV-20260530PAIDnone$250$250$0
29 May 2026Bunnings Group Limited2016/01180250PAIDnone$26$28$0
28 May 2026Dial-A-TarpINV-8350BPAIDnone$477$525$0
28 May 2026Emberforge Pty Ltd014PAIDnone$7,960$8,756$0
27 May 2026Bunnings Group Limited2016/91346806PAIDnone$246$271$0
27 May 2026Bunnings Group Limited2016/01408191PAIDnone$41$46$0
26 May 2026Hafele Australia213708172PAIDnone$133$146$0
25 May 2026Bunnings Group Limited2016/01563384PAIDnone$895$985$0
25 May 2026Bunnings Group Limited2016/01563386PAIDnone$18$20$0
22 May 2026Aspect Decor PaintingINV-1273PAIDnone$3,799$4,178$0
21 May 2026Davis Transport & EarthworksINV-0353PAIDnone$2,804$3,084$0
19 May 2026Bunnings Group Limited2016/01353668PAIDnone$185$204$0
14 May 2026BNA Bricklaying1630PAIDnone$4,970$5,467$0
14 May 2026Bunnings Group Limited2016/01348092PAIDnone$153$168$0
13 May 2026Lenco Bricks Pavers & LogisticsPAIDnone$462$508$0
13 May 2026Wilson & Bradley90556110PAIDnone$286$314$0
12 May 2026Myaree CeramicsORD00346278PAIDnone$3,610$3,971$0
4 May 2026Bunnings Group Limited2016/01554749PAIDnone$196$216$0
2 May 2026Aftermath Limestone & FencingINV-0279PAIDnone$4,784$5,262$0
1 May 2026Emberforge Pty Ltd009PAIDnone$5,600$6,160$0
1 May 2026Bunnings Group Limited2016/01334716PAIDnone$3$3$0
1 May 2026PBM PowerINV-3167PAIDnone$320$352$0
30 Apr 2026Emberforge Pty Ltd009PAIDnone$3,200$3,520$0
30 Apr 2026Instant Products Hire227579PAIDnone$163$179$0
30 Apr 2026Myaree CeramicsORD00345911PAIDnone$588$646$0
29 Apr 2026Bunnings Group Limited2016/01553079PAIDnone$160$176$0
28 Apr 2026Dial-A-TarpINV-8350PAIDnone$697$767$0
27 Apr 2026Jacobson RoofingINV-0037PAIDnone$22,727$25,000$0
23 Apr 2026ImprobuildINV-11448PAIDnone$276$304$0
20 Apr 2026Trident Plumbing & Gas3263PAIDnone$1,148$1,262$0
14 Apr 2026PBM PowerINV-3149PAIDnone$4,357$4,793$0
13 Apr 2026Bunnings Group Limited2016/01314979PAIDnone$35$38$0
13 Apr 2026Jacobson RoofingINV-0036PAIDnone$9,091$10,000$0
10 Apr 2026Emberforge Pty Ltd006PAIDnone$5,750$6,325$0
10 Apr 2026Bunnings Group Limited2016/01311542PAIDnone$279$307$0
9 Apr 2026Versatile Building Products10083447PAIDnone$1,619$1,781$0
8 Apr 2026Bunnings Group Limited2440/01121340PAIDnone$617$679$0
2 Apr 2026Bunnings Group Limited2010/01634730PAIDnone$315$346$0
2 Apr 2026Hansberry Electrical ContractorsPAIDnone$1,591$1,750$0
2 Apr 2026Spartan Handyman ServicesIV000012PAIDnone$2,574$2,574$0
2 Apr 2026Bunnings Group Limited2183/00852517PAIDnone$191$211$0
1 Apr 2026Instant Products Hire226021PAIDnone$180$198$0
1 Apr 2026Perfect Glaze Australia Pty LtdQ2219PAIDnone$17,500$19,250$0
1 Apr 2026Bunnings Group Limited2445/99883254PAIDnone$1,198$1,318$0
1 Apr 2026Instant Waste Management5171988PAIDnone$1,348$1,483$0
1 Apr 2026Bunnings Group Limited2016/01542792PAIDnone$1,539$1,693$0
1 Apr 2026Champion Pest Control11169364PAIDnone$1,400$1,540$0
30 Mar 2026Bunnings Group Limited2016/01541927PAIDnone$364$401$0
26 Mar 2026Holcim Australia9410280542PAIDnone$750$825$0
26 Mar 2026Bunnings Group Limited2016/01540573PAIDnone$43$47$0
25 Mar 2026Davis Transport & EarthworksINV-0335PAIDnone$1,486$1,635$0
24 Mar 2026Holcim Australia9410273785PAIDnone$1,464$1,610$0
24 Mar 2026Big River Group Pty Ltd602-1357826PAIDnone$5,288$5,816$0
21 Mar 2026Holcim Australia9410269813PAIDnone$688$756$0
20 Mar 2026Bunnings Group Limited2016/01538085PAIDnone$41$44$0
19 Mar 2026West Reo Supply2526-OH02PAIDnone$642$706$0
18 Mar 2026OdeionINV-347891-H8V9H4PAIDnone$862$862$0
17 Mar 2026Spartan Handyman ServicesINV-0008PAIDnone$1,418$1,418$0
16 Mar 2026Soils Aint Soils12745-6PAIDnone$302$332$0

Progress claims

ClaimDateStatusInc GSTOutstanding
PC-01122 ODEION - Progress Claim - Deposit9 Mar 2026RECEIVED$28,006$0
PC-01123 Progress Claim - Site Establishment18 Mar 2026RECEIVED$86,172$0
PC-01124 Progress Claim - Slab / Subfloor Completion 25 Mar 2026RECEIVED$64,629$0
PC-01125 Progress Claim - Structural Walls Complete 15 Apr 2026RECEIVED$43,086$0
PC-01126 Progress Claim - Roof Cover Stage 24 Apr 2026RECEIVED$43,086$0
PC-01127 Progress Claim - Wet Area Tiling 20 May 2026RECEIVED$43,086$0
PC-01128 Progress Claim - Cabinetry & Stone Installation 29 May 2026RECEIVED$43,086$0
PC-01129 Progress Claim - Painting & Finishes 30 June 2026RECEIVED$3,884$0
PC-01130 Progress Claim - Practical Completion1 July 2026RECEIVED$29,221$0

Variations

VariationStatusEx GST
VO-1084 CREDIT - Indoor Painting Only - VariationAPPROVED_BY_BUILDER-$18,465
VO-1085 Credit - Stone Feature Works Supply & Install - VariationAPPROVED_BY_BUILDER-$3,528
VO-1087 Credit - Tiles PS Credit & Extra Room TilingAPPROVED_BY_BUILDER-$7,449
VO-1088 Credit - Water Damage Replacement Claim SummaryAPPROVED_BY_BUILDER-$12,395
VO-1089 Variation Credit - AirCon / Solar / LimestoneAPPROVED_BY_BUILDER-$5,794
VO-1090 Cabinetry Mudroom VariationAPPROVED_BY_BUILDER$7,954
VO-1094 CREDIT - Outdoor PaintingAPPROVED_BY_BUILDER-$1,250
VO-1095 CREDIT - Tile Replacement APPROVED_BY_BUILDER-$1,440

Purchase orders (98)

POSupplierDateStatusEx GSTReceived
PO-02788 5221887Instant Waste Management31 Aug 2026RECEIVED · APPROVED$138$138
PO-02912 INV-0531Hua Luan24 Aug 2026RECEIVED · APPROVED$1,450$1,450
PO-03217 235152Instant Products Hire24 Aug 2026RECEIVED · APPROVED$321$321
PO-02904 INV-3347PBM POWER - OLD4 Aug 2026RECEIVED · APPROVED$745$745
PO-02890 2016/01332826Bunnings Group Limited4 Aug 2026RECEIVED · APPROVED$27$27
PO-02901 2435/01380957Bunnings Group Limited31 July 2026RECEIVED · APPROVED$46$46
PO-02895 2016/01328497Bunnings Group Limited31 July 2026RECEIVED · APPROVED$16$16
PO-02792 5211824Instant Waste Management31 July 2026RECEIVED · APPROVED$12$12
PO-02795 233912Instant Products Hire31 July 2026RECEIVED · APPROVED$292$292
PO-02908 1928Perfect Glaze Australia Pty Ltd31 July 2026RECEIVED · APPROVED$875$875
PO-02898 2206/00741247Bunnings Group Limited31 July 2026RECEIVED · APPROVED$56$56
PO-02892 2435/01484410Bunnings Group Limited29 July 2026RECEIVED · APPROVED$19$19
PO-02886 2016/01589746Bunnings Group Limited29 July 2026RECEIVED · APPROVED$201$201
PO-02694 10097891Versatile Building Products28 July 2026RECEIVED · APPROVED$60$60
PO-02800 2016/01325521Bunnings Group Limited28 July 2026RECEIVED · APPROVED$72$72
PO-03034 No referenceCut2Trade Pty Ltd15 July 2026RECEIVED · APPROVED$69$69
PO-02799 2016/01581375Bunnings Group Limited8 July 2026RECEIVED · APPROVED$103$103
PO-02441 1886Perfect Glaze Australia Pty Ltd6 July 2026RECEIVED · APPROVED$120$120
PO-02479 INV-1278Aspect Decor Painting2 July 2026RECEIVED · APPROVED$1,691$1,691
PO-02430 5201779Instant Waste Management1 July 2026RECEIVED · APPROVED$655$655
PO-02443 232343Instant Products Hire30 June 2026RECEIVED · APPROVED$225$225
PO-02417 10094389Versatile Building Products30 June 2026RECEIVED · APPROVED$860$860
PO-02442 2016/01577635Bunnings Group Limited29 June 2026RECEIVED · APPROVED$110$110
PO-02406 INV-0573Decorar Concrete Solutions24 June 2026RECEIVED · APPROVED$10,088$10,088
PO-02445 2206/00791606Bunnings Group Limited17 June 2026RECEIVED · APPROVED$130$130
PO-02474 2443/01467230Bunnings Group Limited17 June 2026RECEIVED · APPROVED$347$347
PO-02501 INV-20260616Peter Randall Tiling Services16 June 2026RECEIVED · APPROVED$900$900
PO-02490 2016/01570328Bunnings Group Limited11 June 2026RECEIVED · APPROVED$134$134
PO-02663 INV-0819InStyle Lacquer9 June 2026RECEIVED · APPROVED$2,507$2,507
PO-02487 2016/01569510Bunnings Group Limited9 June 2026RECEIVED · APPROVED$33$33
PO-02538 1634BNA Bricklaying8 June 2026RECEIVED · APPROVED$1,788$1,788
PO-02407 2016/01569108Bunnings Group Limited8 June 2026RECEIVED · APPROVED$65$65
PO-02535 2016/01370375Bunnings Group Limited4 June 2026RECEIVED · APPROVED$22$22
PO-02531 2016/01567136Bunnings Group Limited3 June 2026RECEIVED · APPROVED$18$18
PO-02664 2334Cushions & Covers2 June 2026RECEIVED · APPROVED$177$177
PO-02528 2016/01368525Bunnings Group Limited2 June 2026RECEIVED · APPROVED$78$78
PO-02548 5191789Instant Waste Management31 May 2026RECEIVED · APPROVED$674$674
PO-02602 229776Instant Products Hire31 May 2026RECEIVED · APPROVED$221$221
PO-02613 INV-20260530Peter Randall Tiling Services30 May 2026RECEIVED · APPROVED$250$100
PO-02582 2016/01180250Bunnings Group Limited29 May 2026RECEIVED · APPROVED$26$26
PO-02493 014Emberforge Pty Ltd28 May 2026RECEIVED · APPROVED$7,960$7,960
PO-02527 INV-8350BDial-A-Tarp28 May 2026RECEIVED · APPROVED$477$477
PO-02560 2016/01408191Bunnings Group Limited27 May 2026RECEIVED · APPROVED$41$41
PO-02562 2016/91346806Bunnings Group Limited27 May 2026RECEIVED · APPROVED$246$246
PO-02665 213708172Hafele Australia26 May 2026RECEIVED · APPROVED$133$133
PO-02555 2016/01563384Bunnings Group Limited25 May 2026RECEIVED · APPROVED$895$895
PO-02557 2016/01563386Bunnings Group Limited25 May 2026RECEIVED · APPROVED$18$18
PO-02408 INV-1273Aspect Decor Painting22 May 2026RECEIVED · APPROVED$3,799$3,799
PO-02543 INV-0353Davis Transport & Earthworks21 May 2026RECEIVED · APPROVED$2,804$2,804
PO-02544 2016/01353668Bunnings Group Limited19 May 2026RECEIVED · APPROVED$185$185
PO-02587 1630BNA Bricklaying14 May 2026RECEIVED · APPROVED$4,970$4,970
PO-02640 2016/01348092Bunnings Group Limited14 May 2026RECEIVED · APPROVED$153$153
PO-02626 No referenceLenco Bricks Pavers & Logistics13 May 2026RECEIVED · APPROVED$462$462
PO-02666 90556110Wilson & Bradley13 May 2026RECEIVED · APPROVED$286$286
PO-02411 ORD00346278Myaree Ceramics12 May 2026RECEIVED · APPROVED$3,610$3,610
PO-02633 1789Perfect Glaze Australia Pty Ltd8 May 2026RECEIVED · APPROVED$7,875$7,875
PO-02637 2016/01554749Bunnings Group Limited4 May 2026RECEIVED · APPROVED$196$196
PO-02374 INV-0279Aftermath Limestone & Fencing2 May 2026RECEIVED · APPROVED$4,784$4,784
PO-02495 009Emberforge Pty Ltd1 May 2026RECEIVED · APPROVED$5,600$5,600
PO-02369 2016/01334716Bunnings Group Limited1 May 2026RECEIVED · APPROVED$3$3
PO-02607 INV-3167PBM POWER - OLD1 May 2026RECEIVED · APPROVED$320$320
PO-02329 ORD00345911Myaree Ceramics30 Apr 2026RECEIVED · APPROVED$588$588
PO-02330 009Emberforge Pty Ltd30 Apr 2026RECEIVED · APPROVED$3,200$3,200
PO-02364 227579Instant Products Hire30 Apr 2026RECEIVED · APPROVED$163$163
PO-02356 2016/01553079Bunnings Group Limited29 Apr 2026RECEIVED · APPROVED$160$160
PO-02392 INV-8350Dial-A-Tarp28 Apr 2026RECEIVED · APPROVED$697$697
PO-02332 INV-0037Jacobson Roofing27 Apr 2026RECEIVED · APPROVED$22,727$22,727
PO-02285 INV-11448Improbuild23 Apr 2026RECEIVED · APPROVED$276$276
PO-02286 3263Trident Plumbing & Gas20 Apr 2026RECEIVED · APPROVED$1,148$1,148
PO-02783 INV-3149PBM POWER - OLD14 Apr 2026RECEIVED · APPROVED$4,357$4,357
PO-02307 INV-0036Jacobson Roofing13 Apr 2026RECEIVED · APPROVED$9,091$9,091
PO-02284 2016/01314979Bunnings Group Limited13 Apr 2026RECEIVED · APPROVED$35$35
PO-02296 006Emberforge Pty Ltd10 Apr 2026RECEIVED · APPROVED$5,750$5,750
PO-02308 2016/01311542Bunnings Group Limited10 Apr 2026RECEIVED · APPROVED$279$279
PO-02300 10083447Versatile Building Products9 Apr 2026RECEIVED · APPROVED$1,619$1,619
PO-02299 2440/01121340Bunnings Group Limited8 Apr 2026RECEIVED · APPROVED$617$617
PO-02304 2183/00852517Bunnings Group Limited2 Apr 2026RECEIVED · APPROVED$191$191
PO-02295 IV000012Spartan Handyman Services2 Apr 2026RECEIVED · APPROVED$2,340$2,340
PO-02303 2010/01634730Bunnings Group Limited2 Apr 2026RECEIVED · APPROVED$315$315
PO-02331 No referenceHansberry Electrical Contractors2 Apr 2026RECEIVED · APPROVED$1,591$1,591
PO-02265 11169364Champion Pest Control1 Apr 2026RECEIVED · APPROVED$1,400$1,400
PO-02297 Q2219Perfect Glaze Australia Pty Ltd1 Apr 2026RECEIVED · APPROVED$17,500$17,500
PO-02306 2445/99883254Bunnings Group Limited1 Apr 2026RECEIVED · APPROVED$1,198$1,198
PO-02301 5171988Instant Waste Management1 Apr 2026RECEIVED · APPROVED$1,348$1,348
PO-02302 226021Instant Products Hire1 Apr 2026RECEIVED · APPROVED$180$180
PO-02305 2016/01542792Bunnings Group Limited1 Apr 2026RECEIVED · APPROVED$1,539$1,539
PO-02298 2016/01541927Bunnings Group Limited30 Mar 2026RECEIVED · APPROVED$364$364
PO-02294 9410280542Holcim Australia26 Mar 2026RECEIVED · APPROVED$750$750
PO-02293 2016/01540573Bunnings Group Limited26 Mar 2026RECEIVED · APPROVED$43$43
PO-02292 INV-0335Davis Transport & Earthworks25 Mar 2026RECEIVED · APPROVED$1,486$1,486
PO-02289 602-1357826Big River Group Pty Ltd24 Mar 2026RECEIVED · APPROVED$5,288$5,288
PO-02291 9410273785Holcim Australia24 Mar 2026RECEIVED · APPROVED$1,464$1,464
PO-02290 9410269813Holcim Australia21 Mar 2026RECEIVED · APPROVED$688$688
PO-02281 2016/01538085Bunnings Group Limited20 Mar 2026RECEIVED · APPROVED$41$41
PO-02282 2526-OH02West Reo Supply19 Mar 2026RECEIVED · APPROVED$642$642
PO-02283 INV-347891-H8V9H4Odeion18 Mar 2026RECEIVED · APPROVED$862$862
PO-02287 INV-0008Spartan Handyman Services17 Mar 2026RECEIVED · APPROVED$1,289$1,289
PO-02288 12745-6Soils Aint Soils16 Mar 2026RECEIVED · APPROVED$302$302

Timesheets (116)

DateWhoHoursTask
4 Aug 2026Liam Doherty8.75Liam Doherty - General Site Labour
4 Aug 2026Nathan Lake5.00Nathan Lake - No description
4 Aug 2026Jordan Greenhill5.00Jordan Greenhill - No description
3 Aug 2026Brad Johns4.00Brad Johns - Site Supervision - Allowance / Week - Rates Based on 3hrs Per Day Site Supervision
3 Aug 2026Telaufue Pou2.17Telaufue Pou - Moving bricks. Filling in trench. Site clean. With Liam.
31 July 2026Telaufue Pou8.00Telaufue Pou - Bunnings first thing for a tool. Then trade assist Nathan and Jordan.
31 July 2026Nathan Lake8.25Nathan Lake - No description
30 July 2026Telaufue Pou6.50Telaufue Pou - Portree for shovel then Valley Close. Removing gravel at front of property to bin.
29 July 2026Telaufue Pou8.83Telaufue Pou - Site clean with Liam.
29 July 2026Nathan Lake8.25Nathan Lake - No description
29 July 2026Liam Doherty8.83Liam Doherty - General Site Labour
28 July 2026Brad Johns1.75Brad Johns - Site Supervision - Allowance / Week - Rates Based on 3hrs Per Day Site Supervision
7 July 2026Mike Jones8.25Mike Jones - Hit list and fire log store
29 June 2026Brad Johns3.67Brad Johns - Site Supervision - Allowance / Week - Rates Based on 3hrs Per Day Site Supervision
29 June 2026Brad Johns3.25Brad Johns - Entry Built In Cabinet - Allowance (includes custom cushion)
29 June 2026Mike Jones8.25Mike Jones - Install fire mantle and other hit lists
26 June 2026Brad Johns2.00Brad Johns - Entry Built In Cabinet - Allowance (includes custom cushion)
26 June 2026Telaufue Pou1.42Telaufue Pou - Dropping off beam from Portree to 3 Valley Close.
26 June 2026Brad Johns3.25Brad Johns - Site Supervision - Allowance / Week - Rates Based on 3hrs Per Day Site Supervision
24 June 2026Liam Doherty9.75Liam Doherty - General Site Labour
23 June 2026Telaufue Pou0.92Telaufue Pou - Dropping off items to window company for powder coating.
17 June 2026Brad Johns2.75Brad Johns - Site Supervision - Allowance / Week - Rates Based on 3hrs Per Day Site Supervision
17 June 2026Brad Johns5.67Brad Johns - Entry Built In Cabinet - Allowance (includes custom cushion)
17 June 2026Jasper Osabofu8.75Jasper Osabofu - Site Clean - General Labour
17 June 2026Liam Doherty10.75Liam Doherty - General Site Labour
16 June 2026Liam Doherty10.25Liam Doherty - General Site Labour
12 June 2026Mike Jones8.25Mike Jones - Final bits on list
11 June 2026Mike Jones9.25Mike Jones - Plastering - Gyprock - Pine MGP10 - 70 x 35
10 June 2026Mike Jones9.25Mike Jones - Misc carpentry list
9 June 2026Brad Johns3.75Brad Johns - Site Supervision - Allowance / Week - Rates Based on 3hrs Per Day Site Supervision

Programme (50 items)

ItemStartEnd
M - 1 - Protection / Cleaning21 Mar 202621 Mar 2026
L - 2 - Demolition / Disconnections21 Mar 202626 Mar 2026
M - 1 - Site Prelims21 Mar 202621 Mar 2026
S - 1 - Asbestos Contractor21 Mar 202621 Mar 2026
L - 1 - Site Works / Temporary Services21 Mar 202626 Mar 2026
M - 4 - Concrete24 Mar 202624 Mar 2026
M - 3 - Site Drainage / Stormwater24 Mar 202624 Mar 2026
S - 3 - Excavator / Bobcat24 Mar 202624 Mar 2026
S - 3 - Soakwell Drainage24 Mar 202624 Mar 2026
L - 4 - Formwork / Concrete24 Mar 202628 Mar 2026
M - 4 - Reinforcement / Reo24 Mar 202624 Mar 2026
M - 4 - Formwork24 Mar 202624 Mar 2026
S - 4 - Termite Treatments24 Mar 202624 Mar 2026
L - 3 - Earthworks / Drainage / Retaining24 Mar 202628 Mar 2026
L - 5 - Wall Construction / Subfloor Framing1 Apr 202613 Apr 2026
S - 5 - Scaffolding1 Apr 20261 Apr 2026
S - 6 - Fall Protection7 Apr 20267 Apr 2026
L - 6 - Ceiling Frame / Roof Frame7 Apr 202618 Apr 2026
M - 6 - Framing / Eaves / Hardware7 Apr 20267 Apr 2026
M - 5 - Cladding10 Apr 202610 Apr 2026
L - 7 - Roof Plumbing / Roof Cover10 Apr 202627 Apr 2026
S - 8 - Electrical27 Apr 202627 Apr 2026
M - 5 - Bricklaying27 Apr 202627 Apr 2026
M - 5 - Internal Door Frames27 Apr 202627 Apr 2026
S - 8 - Plumbing27 Apr 202627 Apr 2026
L - 8 - Demolition / Bricklaying / Internal Framing27 Apr 202629 Apr 2026
S - 9 - Plastering29 Apr 20262 May 2026
M - 10 - Waterproofing4 May 20264 May 2026
S - 10 - Tiling4 May 202618 May 2026
L - 10 - Waterproofing / Tiling / Flooring4 May 20265 May 2026